ESC18-00435
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 4:30:09 PM | P | PART |
|
|
Will need to improve site access to Edgemont to prevent trackout. Permit sign is posted. No spills or discharges.
|
ESC17-01754
| BMP Violation | 9/27/2018 | 9/28/2018 | 9/28/2018 3:51:26 PM | P | PASS |
|
|
New rock construction entrance was installed as requested. Targee and Federal Way eastbound were swept by street sweeper. Storm drain on Federal Way was fitted with a sediment filter bag.
Need to finish installing DI bags on inlet on Targee
|
ESC18-00983
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:42:29 PM | P | CANC |
|
|
rescheduled for site meeting with RP Steve. Mass grading is complete.
|
ESC17-01200
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:41:53 PM | | CANC |
|
|
|
ESC17-00793
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:34:13 PM | | CANC |
|
|
|
ESC15-00094
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:33:49 PM | | CANC |
|
|
|
ESC17-01494
| Aging Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:31:40 PM | | CANC |
|
|
rescheduled for site final
|
ESC17-00985
| Conference | 9/28/2018 | 9/28/2018 | 9/28/2018 3:30:58 PM | P | DONE |
|
|
Permission given to Joel Gilmore with Infinity Pools to construct pool under this active ESC permit. No new ESC permit required.
|
ESC17-01538
| Complaint Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:22:22 PM | P | PEND |
|
|
Stockpiling is still occuring at site. Placement is below grade of vegetated berm and GreenBelt path. Will need to get status update on when stockpiling will be complete. No trackout. No dust issues observed.
|
ESC18-00440
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:03:55 PM | P | PART |
|
|
Pool looks complete. Adajacent lot area that was used for staging and access needs stabilization & vegetation. Will follow up next week. No discharges or trackout to street.
|
ESC17-00836
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 3:01:18 PM | | PASS |
|
|
Vacant lot is still not occupied. Wattle is installed. Disturbed bank has vegetated slightly. Will continue to monitor.
|
ESC16-01205
| Site Final | 9/28/2018 | 9/28/2018 | 9/28/2018 2:30:20 PM | P | PASS |
|
|
Project complete and stabilized. ESC permit conditions satisfied.
|
ESC18-01160
| BMP Violation | 9/27/2018 | 9/28/2018 | 9/28/2018 2:28:08 PM | A | PASS |
|
|
follow up
Stockpile now has a perimeter wattle to capture sediment runoff. DI bag installed on storm drain. Approved.
|
ESC18-00946
| BMP Violation | 9/28/2018 | 9/28/2018 | 9/28/2018 2:17:07 PM | P | FAIL |
|
|
Multiple violations at site. RP has not responded to voicemails.
- Loose dirt in gutter and shoulder and some minor trackout across road. - wattles are not staked and are not overlapping. - rock bag check dam is ripped open - hillside slopes have no BMPs installed
Last warning. Text message sent to RP.
|
ESC18-00462
| BMP Violation | 9/27/2018 | 9/28/2018 | 9/28/2018 2:03:16 PM | A | PASS |
|
|
Gutter was swept as requested. GC Jeff called to state that his son will become a certified RP to be the contact for both the Sherman and Highland View site.
|
ESC18-00494
| General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 11:51:29 AM | P | DONE |
|
|
Demolition complete. New SFH on parcel coverd under ESC18-00435.
|
ESC18-00494
| DOC - Permit Finaled | 9/28/2018 | 9/28/2018 | 9/28/2018 11:50:47 AM | P | PASS |
|
|
|
ESC17-01632
| Conference | 9/28/2018 | 9/28/2018 | 9/28/2018 11:23:16 AM | P | PASS |
|
|
RP is Ken Story - 208.320.3575
Site is now active. ESC permit sign posted on job trailer in SW corner of site. Rock construction entrance is properly installed on 27th Street. Surrounding MS4 storm drains have sediment protection installed. Current dry conditions are allowing truck to exit onto Fairview using existing access points without trackout. RP stated he will install rock construction entrance on Fairview and update SWPPP site map with location as use increases or trackout becomes an issue.
Perimeter wattles installed on west side of project. Additional fill dirt is being hauled onto site by Lurre. Water truck is operating to control fugitive dust.
Approved for construction. Notified RP that they will need to post EPA CGP permit & swppp info.
|
MIS18-00346
| ESC-Conference | 9/5/2018 | 9/28/2018 | 9/27/2018 8:21:33 AM | A | PEND |
|
|
No equipment on site. More geotechnical test pits seem to have been dug.
|