BLD-Final | 8/17/2000 | 8/18/2000 | 8/18/2000 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/17/2000 at 16:38:34. Contact: ###-####.
Cert. of comp. # 19706 issued. 8/18/2000 12:12:23 PM
|
BLD-Grading Inspection | 8/18/2000 | 8/18/2000 | 8/18/2000 | | BOND |
Rita DeYoung
|
|
|
Grading is not complete, but $1000.00 bond has been submitted for incomplete work. Final grading in rear yard is not complete. Grading plan must be revised to indicate where a retaining wall will be built around patio. Also revised site plan must indicate as built location of the driveway so that planning and zoning can ensure it can be approved.
|
BLD-Final | 8/16/2000 | 8/17/2000 | 8/17/2000 | A | CANC |
|
|
|
###-####-- JOHN FN OCC out of time 8/18/2000 7:24:17 AM
|
BLD-Energy code compliance | 5/18/2000 | 5/19/2000 | 5/19/2000 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 05/18/2000 at 11:49:48. Contact: ###-####. c/n removed very poor energy seal 5/19/00 12:11:08 PM
|
BLD-Framing/Rough-in | 5/15/2000 | 5/16/2000 | 5/16/2000 | A | FAIL |
Tom Arcoraci
|
|
|
###-#### See C/notice 5/17/00 1:46:44 PM
|
BLD-Framing/Rough-in | 4/17/2000 | 4/17/2000 | 4/17/2000 | P | FAIL |
Russ Owen
|
|
|
###-#### Engineer to approve to many corrections. 4/18/00 10:50:59 AM
|
BLD-Foundation | 2/16/2000 | 2/17/2000 | 2/17/2000 | A | PART |
Russ Owen
|
|
|
###-#### Subject to engineers approval of (2) horiz plans show (3). In 24" walls. 2/18/00 3:24:30 PM
|
BLD-Footing | 2/11/2000 | 2/11/2000 | 2/11/2000 | P | PASS |
Russ Owen
|
|
|
###-####
|