BLD-Final | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | PASS |
Russ Owen
|
|
|
Final reinspect - Terry, ###-#### - for access push 9876 enter
|
BLD-Final | 6/22/2000 | 6/23/2000 | 6/23/2000 | A | FAIL |
Russ Owen
|
|
|
Eric ###-#### C/N 6/23/00 3:09:20 PM
|
BLD-Energy code compliance | 4/7/2000 | 4/10/2000 | 4/10/2000 | A | PASS |
Russ Owen
|
|
|
Eric, ###-#### - as early as possible please New Mec. check ok as is 4/11/00 10:46:46 AM
|
BLD-Framing/Rough-in | 4/5/2000 | 4/6/2000 | 4/6/2000 | A | PASS |
Russ Owen
|
|
|
re-insp--fr eric ###-#### Ok to insulate frame inspection passed 4/6/00 2:58:15 PM
|
BLD-Framing/Rough-in | 3/30/2000 | 3/30/2000 | 3/30/2000 | P | FAIL |
Wes Worcester
|
|
|
Eric, ###-#### Truss. eng.- bring nail straps- post & base caps transfer paint loads. 3/31/00 8:54:43 AM
|
BLD-Framing/Rough-in | 3/9/2000 | 3/10/2000 | 3/10/2000 | A | PASS |
Jim Storey
|
|
|
###-#### Shear ok. 3/14/00 11:53:06 AM
|
BLD-Framing/Rough-in | 3/8/2000 | 3/9/2000 | 3/9/2000 | A | FAIL |
Tom Arcoraci
|
|
|
mike ###-#### shear nail insp Still nailing- 2nd trip. 3/9/00 11:38:59 AM
|
BLD-Framing/Rough-in | 3/9/2000 | 3/9/2000 | 3/9/2000 | P | FAIL |
Wes Worcester
|
|
|
###-#### No address, no plan, no one on site. 3/14/00 11:01:39 AM
|
BLD-Framing/Rough-in | 3/8/2000 | 3/8/2000 | 3/7/2000 | P | FAIL |
Wes Worcester
|
|
|
###-#### No address- not ready. 3/9/00 11:26:22 AM
|
BLD-Foundation | 2/15/2000 | 2/16/2000 | 2/16/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/15/2000 at 20:00:05. Contact: ###-####. Incomplete rebar ok. 2/16/00 11:50:01 AM
|
BLD-Footing | 2/14/2000 | 2/15/2000 | 2/15/2000 | A | PART |
Tom Arcoraci
|
|
|
###-#### Incom 2/15/00 11:35:12 AM plete. 2/15/00 11:35:20 AM
|