Permanent Occupancy | | 10/18/2000 | 10/18/2000 | | DONE |
|
|
|
|
BLD-Final | 10/12/2000 | 10/13/2000 | 10/13/2000 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/12/2000 at 16:11:30. Contact: ###-####.card to contractor. 10/13/2000 4:11:38 PM
|
BLD-Final | 10/11/2000 | 10/12/2000 | 10/12/2000 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/11/2000 at 15:47:53. Contact: ###-####.
|
FIRE-Final Inspection | 10/11/2000 | 10/12/2000 | 10/12/2000 | P | PASS |
Joe Tawney
|
|
|
###-####. 10/12/2000 8:32:47 AM Reinsp OK for permanant occupancy 10/13/2000 7:51:11 AM
|
BLD-Conference | 10/11/2000 | 10/11/2000 | 10/11/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/11/2000
|
BLD-Conference | 10/6/2000 | 10/6/2000 | 10/6/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/6/2000 stair ok per325
|
BLD-Conference | 10/5/2000 | 10/5/2000 | 10/5/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/5/2000 re c/n, cited 1003 exc for private stairs, will consult 325
|
BLD-Conference | 10/5/2000 | 10/5/2000 | 10/5/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/5/2000
|
BLD-Conference | 10/5/2000 | 10/5/2000 | 10/5/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/5/2000
|
BLD-Conference | 9/29/2000 | 10/2/2000 | 10/2/2000 | A | PASS |
Carl Dependahl
|
|
|
10/2/2000 10:20:38 AM w/ bldr re demising wall. will advise after chk w/mgmt. 10/2/2000 10:21:39 AM
|
BLD-Final | 10/2/2000 | 10/2/2000 | 10/2/2000 | A | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/2/2000 c/n issued, need other sig's, stairs, rails, finish, etc.
|
FIRE-Final Inspection | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | FAIL |
Joe Tawney
|
|
|
Final Fail C/N issued. 10/2/2000 7:55:14 AM
|
FIRE-Conference | 9/22/2000 | 9/22/2000 | 9/22/2000 | P | PART |
Joe Tawney
|
|
|
###-#### scott Conf on fire code items for final insp 9/25/2000 7:42:12 AM
|
BLD-Conference | 9/13/2000 | 9/13/2000 | 9/13/2000 | P | PASS |
Carl Dependahl
|
|
|
scott-- ###-#### conf insp; re prev c/n...show specs for grid, add spacer bars, etc. status of demising wall unclear for elec panels. 9/13/2000 11:34:03 AM
|
BLD-Framing/Rough-in | 9/11/2000 | 9/11/2000 | 9/11/2000 | P | FAIL |
|
|
|
CEILING GRID -SCOTT ###-#### need better wire wrapping need pop riviting need to complete perimeter slack wiring and install all light fixtures, elec panel box in tenant demising wall too large of an opening c/nissued 9/11/2000 4:21:17 PM
|
BLD-Wall cover | 8/15/2000 | 8/16/2000 | 8/16/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/15/2000 at 16:09:52. Contact: .bath rm, draft stops ok 8/16/2000 12:11:24 PM
|
BLD-Wall cover | 8/14/2000 | 8/15/2000 | 8/15/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/14/2000 at 15:32:24. Contact: . Int parts ok 8/15/2000 4:22:43 PM
|
BLD-Wall cover | 8/14/2000 | 8/14/2000 | 8/14/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/14/2000 at 08:06:51. Contact: .recall when complete 8/14/2000 4:42:40 PM
|
BLD-Conference | 7/18/2000 | 7/18/2000 | 7/18/2000 | P | PASS |
Carl Dependahl
|
|
|
###-#### Will submit info re: tile @ rest rm. glazed? 7/19/00 9:59:47 AM
|
BLD-Framing/Rough-in | 7/11/2000 | 7/12/2000 | 7/12/2000 | P | PART |
Carl Dependahl
|
|
|
###-#### Bsmt. lid, ext. wall frame/nailing ok ok to insul. 7/13/00 11:32:17 AM
|
BLD-Framing/Rough-in | 7/6/2000 | 7/7/2000 | 7/7/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 07:57:59. Contact: . Need clarify int. shearwall. 7/10/00 10:29:06 AM
|
BLD-Framing/Rough-in | 6/28/2000 | 6/29/2000 | 6/29/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/28/2000 at 09:52:20. Contact: ###-####. roof nailing 6/30/00 8:14:24 AM
|
BLD-Other | 6/28/2000 | 6/29/2000 | 6/28/2000 | A | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/28/2000 at 09:18:14. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/28/2000 at 09:50:34.
|
BLD-Framing/Rough-in | 6/28/2000 | 6/28/2000 | 6/28/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/28/2000 at 10:08:36. Contact: ###-####. recall n/r 6/29/00 10:01:16 AM
|
BLD-Footing | 5/9/2000 | 5/10/2000 | 5/10/2000 | A | PART |
Carl Dependahl
|
|
|
scott ###-#### ft SW corner ftgs. 5/11/00 11:48:43 AM
|
BLD-Footing | 5/8/2000 | 5/9/2000 | 5/9/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/08/2000 at 16:10:25. Contact: . cancel =re-schdeuled No plan available, trailer locked. 5/11/00 10:57:08 AM
|
BLD-Foundation | 4/24/2000 | 4/25/2000 | 4/26/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/24/2000 at 08:47:08. Contact: . late pm Scott ###-#### West fdn. wall(s) ok 4/28/00 8:36:59 AM
|
BLD-Foundation | 4/19/2000 | 4/20/2000 | 4/20/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/19/2000 at 11:50:42. Contact: . North & west side ftg's. ok; verts ok. 4/21/00 9:26:01 AM
|
BLD-Foundation | 4/18/2000 | 4/19/2000 | 4/19/2000 | A | PART |
Carl Dependahl
|
|
|
###-#### Bsmt. wall....eng's approval for beam pockets to follow. 4/19/00 1:52:58 PM
|
BLD-Footing | 4/12/2000 | 4/12/2000 | 4/12/2000 | P | PART |
Carl Dependahl
|
|
|
basment footings last thing this afternoon Scott ###-#### Basement ftg's only. No spec. insp., 2500 PSI design. 4/17/00 1:32:09 PM
|