BLD-Final | 4/27/2000 | 4/28/2000 | 4/28/2000 | A | PASS |
Russ Owen
|
|
|
key over front door ###-####
|
BLD-Final | 4/26/2000 | 4/27/2000 | 4/27/2000 | A | FAIL |
|
|
|
###-#### key is over front door energy code ext seal not complete 4/27/00 10:48:04 AM
|
BLD-Energy code compliance | 3/22/2000 | 3/23/2000 | 3/23/2000 | P | PASS |
Russ Owen
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/22/2000 | 3/23/2000 | 3/23/2000 | P | PART |
Russ Owen
|
|
|
2 corrections under floor not done C/N posted 3/24/00 1:08:17 PM
|
BLD-Framing/Rough-in | 3/21/2000 | 3/22/2000 | 3/22/2000 | A | FAIL |
Wes Worcester
|
|
|
###-#### 2 page- Header at HVAC crawl- not in crawl (place up or down carrying roof load) Truss engineering & engineering wrong- Unable to complete under floor inspection 3/22/00 1:47:03 PM
|
BLD-Framing/Rough-in | 3/15/2000 | 3/15/2000 | 3/15/2000 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/15/2000 at 07:08:24. Contact: ###-####. Ok to side 3/16/00 1:28:18 PM
|
BLD-Framing/Rough-in | 3/14/2000 | 3/14/2000 | 3/14/2000 | P | FAIL |
Wes Worcester
|
|
|
john ###-#### shear nail insp Unable to make 2nd trip- called to reschedule. 3/16/00 11:27:08 AM
|
BLD-Framing/Rough-in | 3/13/2000 | 3/13/2000 | 3/13/2000 | P | FAIL |
Wes Worcester
|
|
|
###-#### shear nailing Still nailing @ 4 pm- not close to being ready. 3/14/00 1:45:42 PM
|
BLD-Foundation | 2/22/2000 | 2/23/2000 | 2/23/2000 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/22/2000 at 18:33:43. Contact: ###-####.
|
BLD-Footing | 2/18/2000 | 2/22/2000 | 2/22/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/18/2000 at 17:27:59. Contact: ###-####. No plans at the site, work appears ok. 2/23/00 1:55:29 PM
|