BLD-Final | 4/13/2000 | 4/14/2000 | 4/14/2000 | P | PASS |
Carl Dependahl
|
|
|
###-#### late pm "Scope-of-work" complete; received spec. insp. for masonry lintel ok. 4/17/00 1:34:36 PM
|
FIRE-Final Inspection | 4/13/2000 | 4/14/2000 | 4/14/2000 | A | PASS |
Joe Tawney
|
|
|
Keith ###-#### late am Reinsp. ok for perm. occ. 4/14/00 1:44:38 PM
|
Permanent Occupancy | | 4/14/2000 | 4/14/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/12/2000 | 4/13/2000 | 4/13/2000 | P | FAIL |
Joe Tawney
|
|
|
KEith ###-#### Final fail C/N issued.
4/14/00 10:56:13 AM
|
FIRE-Final Inspection | 4/13/2000 | 4/13/2000 | 4/13/2000 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final fail C/N issued. 4/14/00 10:56:35 AM
|
FIRE-Sprinkler Rough-in | 3/23/2000 | 3/24/2000 | 3/24/2000 | A | PART |
Joe Tawney
|
|
|
KEITH-- ###-#### R/I FIRE Conf. on AHU duct detectors 3/24/00 1:09:34 PM
|
BLD-Framing/Rough-in | 3/21/2000 | 3/22/2000 | 3/22/2000 | A | FAIL |
Carl Dependahl
|
|
|
###-#### C/N, need HVAC & fire. 3/22/00 3:21:26 PM
|
BLD-Framing/Rough-in | 3/20/2000 | 3/21/2000 | 3/21/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### late pm Recall after plbg. 3/22/00 3:20:14 PM
|