BLD-Conference | 2/27/2001 | 2/27/2001 | 2/27/2001 | P | PASS |
Carl Dependahl
|
|
|
Mel Perez ###-#### ;submit detail for elev shaft penetrations; awaiting floor penetration details faxed?? 2/27/2001 5:52:58 PM
|
BLD-Foundation | 6/15/2000 | 6/16/2000 | 6/16/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 06/15/2000 at 13:02:26. Contact: ###-####. ok to pour at grade level with sp insp approvals 6/16/00 11:38:08 AM
|
BLD-Concrete | 5/31/2000 | 5/31/2000 | 5/31/2000 | A | FAIL |
|
|
|
Added by Inspector: 338 On 5/31/00 ot ready for inspection, still setting forms and placing r-bar sp insp not on site yet
|
BLD-Foundation | 5/30/2000 | 5/31/2000 | 5/31/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/30/2000 at 14:43:10. Contact: ###-####. f on 12 line to j to 10 line on j line to h la 10.5 to 11 to f/12 line 6/1/00 9:14:57 AM
|
BLD-Foundation | 5/10/2000 | 5/11/2000 | 5/11/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/10/2000 at 15:04:23. Contact: ###-####. with sp insp spprovals 5/11/00 5:48:18 PM
|
BLD-Foundation | 5/5/2000 | 5/8/2000 | 5/9/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/05/2000 at 16:21:47. Contact: ###-####.
|
BLD-Foundation | 5/3/2000 | 5/4/2000 | 5/4/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/03/2000 at 16:33:16. Contact: ###-####. with sp insp approvals 5/4/00 6:18:20 PM
|
BLD-Foundation | 5/1/2000 | 5/2/2000 | 5/2/2000 | A | PART |
|
|
|
###-#### east most part of A line footing, and footers onpads c/5, B.5/8, and B.5 /9 5/2/00 4:01:53 PM
|
BLD-Foundation | 4/27/2000 | 4/28/2000 | 4/28/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/27/2000 at 07:52:18. Contact: ###-####. pending report. 4/28/00 8:50:39 AM
|
BLD-Foundation | 4/27/2000 | 4/28/2000 | 4/28/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 04/27/2000 at 07:52:18. Contact: ###-####.
|
BLD-Foundation | 4/27/2000 | 4/27/2000 | 4/27/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 04/27/2000 at 07:51:31. Contact: ###-####. misc ftings, west elev. shaft nisc footings cnting 2 and 1 4/27/00 11:44:52 AM
|
BLD-Foundation | 4/20/2000 | 4/24/2000 | 4/24/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 04/20/2000 at 16:18:56. Contact: ###-####. pad on c/7;e7; e/6;c/6 and wall 1-line tru 4 line at c9 r-ar placed ok to pour with sp insp approvals 4/24/00 1:12:08 PM
|
BLD-Footing | 4/19/2000 | 4/19/2000 | 4/19/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 04/19/2000 at 10:05:01. Contact: ###-####. large footing at 5 line from south of c9 north aprox 45 feet, for the brace frame 04/20/2000 8:43:48 AM
|
BLD-Foundation | 4/14/2000 | 4/17/2000 | 4/17/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 04/14/2000 at 12:54:33. Contact: ###-####. c.910 to 11.9 04/17/2000
|
BLD-Concrete | 4/17/2000 | 4/12/2000 | 4/12/2000 | A | PART |
|
|
|
Added by Inspector: 338 On 04/17/2000 first lift of the elevator shaft walls from thebsmt grnd level (elev. pit)
|
BLD-Foundation | 4/6/2000 | 4/10/2000 | 4/10/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 04/06/2000 at 10:01:25. Contact: ###-####. a-line from 11 to 12 line and 12 line from a to c line brace frame footing poured 4/7-00 04/10/2000
|
BLD-Footing | 4/6/2000 | 4/7/2000 | 4/7/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/06/2000 at 09:56:26. Contact: ###-####. rebar west basement wall sec. ok pending special insp. report. 4/6/00
|
BLD-Footing | 4/4/2000 | 4/4/2000 | 4/4/2000 | P | PART |
|
|
|
harry ###-#### footing pade; c/10; c/3; c/2; c/1.7 04/04/2000
|
BLD-Footing | 3/31/2000 | 4/3/2000 | 4/3/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 03/31/2000 at 11:47:32. made ok to pour with sp insp approvals, elevator pit either side of match line for area 1 & area 2 (footings) water stop placed 04/03/2000
|
BLD-Footing | 3/24/2000 | 3/27/2000 | 3/27/2000 | A | PART |
|
|
|
HARRY ###-#### FT col pads b/10-b/8 and c/8 03/27/2000 3:44:00 PM 03/27/2000 3:44:21 PM 03/27/2000 3:45:49 PM
|
BLD-Foundation | 3/21/2000 | 3/22/2000 | 3/22/2000 | A | PART |
|
|
|
###-####\\b and c colum 11 11.3 and 10 on b line. ok to pour with sp insp approvals. 03/22/2000 1:58:41 PM
|
BLD-Foundation | 3/20/2000 | 3/22/2000 | 3/22/2000 | P | FAIL |
|
|
|
column line 1 A to D column line D 1 to 4 column 03/22/2000 2:02:51 PM dewater required this area prior to pour 03/22/2000 2:03:32 PM
|
BLD-Conference | 3/20/2000 | 3/20/2000 | 3/20/2000 | A | FAIL |
|
|
|
GRID LINE FROM 12 LINE TO 8 AT D LINE POURED W/O INSP BY BOISE CITY ON 3/17/00. i EXPLAINED TO MEL WITH MKC THAT THIS IS NOT ACCEPTABLE AND THAT REQUESTS FOR INSPECTIONS MUST BE MADE PRIOR TO PLACING CONCRETE ON THIS PROJECT. THE NEXT INSP FOR 3/21/00 WAS CALLED FOR IN MY PRESENCE. 338
|
BLD-Footing | 3/16/2000 | 3/16/2000 | 3/16/2000 | A | PART |
|
|
|
mel ###-#### column d 8-12 line
|
BLD-Foundation | 3/15/2000 | 3/15/2000 | 3/15/2000 | A | PART |
|
|
|
column line A from 8 to 12 Mel ###-#### with mel, harry, ron, and mike, discussed concrete pour scheduling and requests for same 03/15/2000 11:36:55 AM column line A from 8 to 12 and from A to D on 12 line all r-bar ok forms ok okto pour also approved by the sp insp m. spiker. recieved reduced plans from Mel. Mel ###-#### with mel, harry, ron, and mike, discussed concrete pour scheduling and requests for same 03/15/2000 11:36:55 AM 03/17/2000 9:06:57 AM
|
BLD-Conference | 3/10/2000 | 3/10/2000 | 3/10/2000 | P | PART |
|
|
|
met with harry an d mel on the jobsite meeting to be set up for next week befor pouring concrete 03/15/2000 11:32:59 AM
|