BLD-Final | 10/25/2000 | 10/26/2000 | 10/26/2000 | A | PASS |
Jim Sly
|
|
|
fn -ty- ###-####
|
BLD-Final | 10/24/2000 | 10/24/2000 | 10/24/2000 | P | FAIL |
Jim Sly
|
|
|
FN --TYE-- --###-#### FN --TYE C/N issued -- --###-#### 10/24/2000 4:37:59 PM
|
BLD-Energy code compliance | 8/10/2000 | 8/11/2000 | 8/11/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 17:12:44. Contact: . NR 8/11/2000 3:21:59 PM
|
BLD-Framing/Rough-in | 8/10/2000 | 8/11/2000 | 8/11/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 17:09:41. Contact: .
|
BLD-Framing/Rough-in | 8/8/2000 | 8/9/2000 | 8/9/2000 | A | FAIL |
Jim Sly
|
|
|
tye ###-#### C/N issued. 8/9/2000 12:31:50 PM
|
BLD-Framing/Rough-in | 8/4/2000 | 8/7/2000 | 8/7/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/04/2000 at 10:42:05. Contact: ###-####. C/N..Need Elect, Mech and plans. 8/7/2000 9:28:18 AM
|
BLD-Final | 8/4/2000 | 8/7/2000 | 8/4/2000 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/04/2000 at 10:36:42. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 08/04/2000 at 10:40:38.
|
BLD-Framing/Rough-in | 6/28/2000 | 6/28/2000 | 6/28/2000 | P | PART |
Jim Sly
|
|
|
gib ###-#### shear Shear nail OK...C/N on strap. 6/28/00 1:48:11 PM
|
BLD-Foundation | 5/25/2000 | 5/25/2000 | 5/25/2000 | P | PASS |
Jim Sly
|
|
|
Dave Cox ###-#### Appears ok per appr. plan 5/26/00 12:16:27 PM
|
BLD-Footing | 5/22/2000 | 5/23/2000 | 5/23/2000 | A | FAIL |
Jim Sly
|
|
|
###-####--dave ft Early start footing- min. rebar & setbacks appear ok. 5/23/00 2:12:29 PM
|