BLD-Final | 9/20/2000 | 9/20/2000 | 9/20/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 10:25:41. Contact: ###-####.
|
BLD-Energy code compliance | 7/21/2000 | 7/24/2000 | 7/24/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/21/2000 at 16:03:52. Contact: ###-####. Underfloor at final. Frame pass 7/24/00 9:46:24 AM
|
BLD-Energy code compliance | 7/19/2000 | 7/20/2000 | 7/20/2000 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 07:15:35. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/19/2000 | 7/19/2000 | 7/19/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 07:14:51. Contact: ###-####. C/N...fail Wattsun shows R-13 + R-5 (walls fully sheathed). 7/20/00 9:44:23 AM
|
BLD-Framing/Rough-in | 7/18/2000 | 7/18/2000 | 7/18/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/18/2000 at 07:07:28. Contact: ###-####. Need Energy report 7/18/00 4:19:59 PM
|
BLD-Framing/Rough-in | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | FAIL |
|
|
|
framing approved sticker n widow not by me will not approve same 7/13/2000 5:33:32 PM
|
BLD-Framing/Rough-in | 7/11/2000 | 7/12/2000 | 7/12/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 17:50:05. Contact: ###-####. Keep C/N; renail, eng'g for "straps" (too short). 7/13/00 11:26:37 AM
|
BLD-Framing/Rough-in | 7/11/2000 | 7/11/2000 | 7/11/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 09:42:16. Contact: ###-####. c/n issued improper straps and nails, por nailing ofbrace panels 7/11/00 1:17:12 PM
|
BLD-Framing/Rough-in | 7/10/2000 | 7/10/2000 | 7/10/2000 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/10/2000 at 09:55:51. Contact: ###-####. No plans 7/11/00 11:39:44 AM
|
BLD-Foundation | 6/15/2000 | 6/16/2000 | 6/16/2000 | A | PASS |
Jim Sly
|
|
|
|
BLD-Footing | 6/15/2000 | 6/15/2000 | 6/15/2000 | P | PART |
Jim Sly
|
|
|
late pm ###-####
|