BLD-Final | 8/30/2002 | 8/30/2002 | 8/30/2002 | P | PASS |
Tony Young
|
|
|
Joe ###-####
|
Permanent Occupancy | | 8/30/2002 | 8/30/2002 | | DONE |
|
|
|
|
BLD-Final | 2/28/2002 | 3/1/2002 | 3/1/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/28/2002 at 16:31:08. Contact: ###-####...c/n, air seal, grading/retaining wall; patch/seal 1hr separations. 3/1/2002 11:06:36 AM
|
FIRE-Final Inspection | 2/28/2002 | 2/28/2002 | 2/28/2002 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/28/2002 at 09:54:58. Contact: ###-####.
|
BLD-Energy code compliance | 10/30/2001 | 10/31/2001 | 10/31/2001 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/30/2001 at 16:11:42. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/26/2001 | 10/29/2001 | 10/29/2001 | A | PART |
Tony Young
|
|
|
###-#### CHRIS
ok to insulate, need some areas completed for draft and fire stopped 10/29/2001 12:33:19 PM
|
BLD-Framing/Rough-in | 10/22/2001 | 10/22/2001 | 10/22/2001 | P | FAIL |
Tony Young
|
|
|
###-#### chris
c/n posted,, need to finish 1 hr in floor/ ceiling for ducting, etc.,, no insulation allowed, need to reinspect 10/22/2001 2:27:12 PM
|
BLD-Footing | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Tony Young
|
|
|
chris ###-#### ft insp
interior ftg., ok w/ verbal corrections 8/23/2001 3:05:23 PM
|
BLD-Foundation | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | PART |
Tony Young
|
|
|
###-#### chris
wip, verbal corrections 8/10/2001 11:08:36 AM
|
BLD-Footing | 8/7/2001 | 8/8/2001 | 8/8/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/07/2001 at 15:41:12. Contact: ###-####.
|