Permanent Occupancy | | 4/4/2001 | 4/4/2001 | | DONE |
|
|
|
|
BLD-Final | 4/3/2001 | 4/3/2001 | 4/3/2001 | P | PASS |
Carl Dependahl
|
|
|
Pete ###-#### card to contractor. 4/3/2001 5:00:56 PM
|
BLD-Final | 2/2/2001 | 2/5/2001 | 2/5/2001 | A | FAIL |
Carl Dependahl
|
|
|
Pete ###-####; c/n, need statement for door hdwe, achd?? ok for t/o. 2/5/2001 12:34:48 PM
|
BLD-Final | 2/1/2001 | 2/2/2001 | 2/2/2001 | A | FAIL |
Carl Dependahl
|
|
|
###-####; need fire, etc. recall 2/2/2001 9:35:16 AM
|
FIRE-Final Inspection | 2/2/2001 | 2/2/2001 | 2/2/2001 | P | PASS |
Rick Jackson
|
|
|
building is left open Pete ###-####
|
BLD-Other | | | 2/2/2001 | | PEND |
|
|
|
Final signoff OK'd/
|
BLD-Framing/Rough-in | 12/15/2000 | 12/15/2000 | 12/15/2000 | P | PART |
Carl Dependahl
|
|
|
###-####; need hvac r/i; consult arch. re lid vapor barrier, framing to be at 12" oc if green bd used, ok otherwise. 12/15/2000 2:13:25 PM
|
BLD-Framing/Rough-in | 11/28/2000 | 11/28/2000 | 11/28/2000 | P | PART |
Carl Dependahl
|
|
|
fr insp pete-- ###-#### roof, struct sheathing ok 11/28/2000 4:47:04 PM
|
BLD-Concrete | 11/14/2000 | 11/14/2000 | 11/14/2000 | P | PART |
Carl Dependahl
|
|
|
block walls\###-####, 2nd lift ok 11/14/2000 12:03:09 PM
|
BLD-Concrete | 11/13/2000 | 11/13/2000 | 11/13/2000 | P | PART |
Carl Dependahl
|
|
|
###-####
|
BLD-Concrete | 11/2/2000 | 11/2/2000 | 11/2/2000 | P | PASS |
Tom Arcoraci
|
|
|
###-####
|
BLD-Footing | 10/30/2000 | 10/31/2000 | 10/31/2000 | A | PASS |
Jim Storey
|
|
|
Pete ###-####
|