BLD-Final | 2/16/2001 | 2/20/2001 | 2/20/2001 | A | PASS |
Alan Hauser
|
|
|
corrections done, c/c#19850 2/20/2001 11:18:28 AM
|
BLD-Grading Inspection | 2/14/2001 | 2/14/2001 | 2/14/2001 | | BOND |
Rita DeYoung
|
|
|
Rough grading has been completed. Fine grading and revegetation have not. For this the engineer has recommended a $700.00 bond. Upon receipt of this the grading is conditionally approved.
|
BLD-Final | 2/9/2001 | 2/9/2001 | 2/9/2001 | P | FAIL |
Tony Young
|
|
|
###-####
c/n posted, p.w. final, address, fire door,vents, plans, past inspections-c/n, clean under floor 2/9/2001 1:19:20 PM
|
BLD-Framing/Rough-in | 10/11/2000 | 10/12/2000 | 10/12/2000 | A | PART |
Tony Young
|
|
|
FR TOM ###-####
ok to insulate, c/n posted 10/12/2000 12:25:18 PM
|
BLD-Framing/Rough-in | 9/13/2000 | 9/14/2000 | 9/14/2000 | A | PASS |
Tony Young
|
|
|
tom ###-#### shear nail insp
passed ,, ok to side 9/14/2000 10:54:38 AM
|
BLD-Framing/Rough-in | 9/13/2000 | 9/13/2000 | 9/13/2000 | P | PART |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 9/13/2000 shear wall
ext. shear ok ,, verify int. shear dry wall later 9/13/2000 12:44:24 PM
|
BLD-Foundation | 7/24/2000 | 7/24/2000 | 7/24/2000 | P | PART |
Tony Young
|
|
|
###-#### Work in progress appears ok- w/verbal corrections 7/25/00 9:35:54 AM
|
BLD-Footing | 7/20/2000 | 7/21/2000 | 7/21/2000 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/20/2000 at 13:45:52. .
|
BLD-Footing | 7/19/2000 | 7/20/2000 | 7/20/2000 | A | FAIL |
Tony Young
|
|
|
Tim ###-#### Need soil eng. report 7/21/00 9:08:39 AM
|