BLD-Final | 10/13/2000 | 10/13/2000 | 10/13/2000 | | PASS |
|
|
|
Final, ok for perm. occ.
|
FIRE-Final Inspection | 10/12/2000 | 10/13/2000 | 10/13/2000 | A | PASS |
Joe Tawney
|
|
|
###-####. Reinsp OK for permanant occupancy 10/13/2000 12:08:16 PM
|
Permanent Occupancy | | 10/13/2000 | 10/13/2000 | | DONE |
|
|
|
|
BLD-Final | 10/11/2000 | 10/11/2000 | 10/11/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/11/2000 at 08:12:01. Contact: ###-####. OK FOR TEMP OCC. ONLY. 10/11/2000 3:20:01 PM
|
FIRE-Final Inspection | 10/11/2000 | 10/11/2000 | 10/11/2000 | P | PART |
Joe Tawney
|
|
|
###-####. Reinsp OK for temporary Occupancy Alarm silence & door hdwre 10/11/2000 12:27:05 PM
|
BLD-Final | 10/9/2000 | 10/10/2000 | 10/10/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/09/2000 at 17:31:29. Contact: ###-####. NR 10/10/2000 4:33:37 PM
|
FIRE-Final Inspection | 10/9/2000 | 10/10/2000 | 10/10/2000 | P | FAIL |
Joe Tawney
|
|
|
###-####. Reinsp Fail Not ready 10/10/2000 5:54:01 PM
|
BLD-Final | 10/6/2000 | 10/6/2000 | 10/6/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/06/2000 at 08:29:47. Contact: ###-####. NR 10/6/2000 4:40:56 PM
|
FIRE-Final Inspection | 10/6/2000 | 10/6/2000 | 10/6/2000 | P | FAIL |
Joe Tawney
|
|
|
###-####. 10/6/2000 12:11:29 PM
|
BLD-Final | 10/5/2000 | 10/5/2000 | 10/5/2000 | P | FAIL |
Jim Sly
|
|
|
###-#### fire is also going out pm today
|
FIRE-Final Inspection | 10/5/2000 | 10/5/2000 | 10/5/2000 | P | CANC |
Joe Tawney
|
|
|
###-#### Cancel To be rescheduled 10/5/2000 12:07:49 PM
|
BLD-Final | 10/2/2000 | 10/2/2000 | 10/2/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/02/2000 at 08:29:02. Contact: ###-####.
|
FIRE-Final Inspection | 10/2/2000 | 10/2/2000 | 10/2/2000 | P | FAIL |
Joe Tawney
|
|
|
###-####. Reinsp Fail Access control doors 10/3/2000 7:39:46 AM
|
BLD-Final | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/28/2000 at 13:23:27. Contact: ###-####.
|
FIRE-Final Inspection | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | FAIL |
Joe Tawney
|
|
|
###-####. Reinsp Fail C/N issued 9/29/2000 12:08:38 PM
|
BLD-Final | 9/27/2000 | 9/28/2000 | 9/27/2000 | A | CANC |
Jim Sly
|
|
|
GREG-- ###-#### FN OCC--CANCEL PER GREG WITH STEED
|
FIRE-Final Inspection | 9/27/2000 | 9/27/2000 | 9/27/2000 | P | FAIL |
Joe Tawney
|
|
|
###-#### GREG FIRE FN Fail Not ready for final 9/28/2000 8:07:01 AM
|
FIRE-Sprinkler Rough-in | 9/27/2000 | 9/27/2000 | 9/27/2000 | P | FAIL |
Joe Tawney
|
|
|
R/I -GREG ###-#### Fail Approvedspklr plans not on site 9/28/2000 8:06:15 AM 9/28/2000 8:06:32 AM
|
FIRE-Final Inspection | 9/21/2000 | 9/21/2000 | 9/21/2000 | P | FAIL |
Joe Tawney
|
|
|
fire fn gregg-- ###-#### Fail Not ready for final 9/22/2000 7:57:12 AM
|
BLD-Framing/Rough-in | 9/15/2000 | 9/19/2000 | 9/19/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/15/2000 at 07:26:06. Contact: ###-####. ceiling grid OK 9/19/2000 11:35:11 AM
|
BLD-Framing/Rough-in | 9/14/2000 | 9/15/2000 | 9/15/2000 | A | PART |
Jim Sly
|
|
|
GREGG ###-#### PARTIAL GRID INSP Partial ceiling grid insp....Gen. office (Lrg. Rm.) Phase 1 OK. 9/15/2000 11:27:32 AM
|
BLD-Framing/Rough-in | 9/13/2000 | 9/13/2000 | 9/13/2000 | P | FAIL |
Tom Arcoraci
|
|
|
ceiling grid ###-#### not ready 9/13/2000 1:40:43 PM
|
BLD-Framing/Rough-in | 8/23/2000 | 8/24/2000 | 8/24/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 09:12:59. Contact: ###-####. Fire resist treat wood interior walls (backing) OKd by George S. 8/24/2000 10:13:54 AM
|
BLD-Framing/Rough-in | 8/15/2000 | 8/16/2000 | 8/16/2000 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/15/2000 at 16:41:50. Contact: ###-####. C/N..Need detail for firestop ten dem wall. 8/16/2000 10:44:51 AM
|