BLD-Final | 8/31/2000 | 8/31/2000 | 8/31/2000 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 08/31/2000 at 06:51:03. Contact: ###-####.
|
Permanent Occupancy | | 8/31/2000 | 8/31/2000 | | DONE |
|
|
|
|
BLD-Final | 8/30/2000 | 8/30/2000 | 8/30/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/30/2000 at 08:21:28. Contact: ###-####. NR 8/30/2000 3:41:09 PM
|
BLD-Final | 8/29/2000 | 8/29/2000 | 8/29/2000 | P | NR |
Tom Arcoraci
|
|
|
greg-- ###-#### fn occ no heating final 8/29/2000 4:41:37 PM
|
BLD-Final | 8/28/2000 | 8/29/2000 | 8/29/2000 | A | CANC |
Jim Sly
|
|
|
gregg ###-#### unit 130---cancel per greg
|
FIRE-Final Inspection | 8/28/2000 | 8/29/2000 | 8/29/2000 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 08/28/2000 at 16:49:42. Contact: ###-####. Reinsp OK for permanant occupancy 8/29/2000 1:48:42 PM
|
BLD-Conference | 8/28/2000 | 8/28/2000 | 8/28/2000 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/28/2000 w steed re hvac
|
FIRE-Final Inspection | 8/28/2000 | 8/28/2000 | 8/28/2000 | P | FAIL |
Joe Tawney
|
|
|
Gregg ###-#### unit 130 Final fail fire ext 8/29/2000 1:46:16 PM
|
BLD-Framing/Rough-in | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | PASS |
Jim Sly
|
|
|
framing for wall cover ###-####
|
BLD-Framing/Rough-in | 8/11/2000 | 8/11/2000 | 8/11/2000 | P | PASS |
Jim Sly
|
|
|
ACUSTIC GRID-- ###-#### -GREG
|
BLD-Framing/Rough-in | 8/10/2000 | 8/10/2000 | 8/10/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 08:30:34. Contact: ###-####. NR 8/10/2000 3:37:40 PM
|
FIRE-Sprinkler Rough-in | 8/10/2000 | 8/10/2000 | 8/10/2000 | P | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 08:29:03. Contact: ###-####. Ok on sprinkler R/I 8/11/00 12:01:18 PM
|