BLD-Final | 10/2/2000 | 10/3/2000 | 10/3/2000 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/02/2000 at 17:47:38. Contact: .
|
BLD-Energy code compliance | 9/8/2000 | 9/8/2000 | 9/8/2000 | P | PART |
Carl Dependahl
|
|
|
###-####; chk floor ins at final 9/8/2000 12:24:32 PM
|
BLD-Framing/Rough-in | 9/8/2000 | 9/8/2000 | 9/8/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/8/2000 ok
|
BLD-Framing/Rough-in | 9/6/2000 | 9/7/2000 | 9/7/2000 | P | PART |
Carl Dependahl
|
|
|
TIM-- ###-#### FR INSP ` 9/7/2000 12:16:33 PMok to insul, finish dry-in now. 9/7/2000 5:13:10 PM
|
BLD-Foundation | 8/23/2000 | 8/24/2000 | 8/24/2000 | A | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 10:21:36. Contact: ###-####.
|
BLD-Foundation | 8/24/2000 | 8/24/2000 | 8/24/2000 | P | PART |
Carl Dependahl
|
|
|
adam ###-####
|
BLD-Footing | 8/23/2000 | 8/23/2000 | 8/23/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 10:20:55. Contact: ###-####.no plans, excav only 8/23/2000 1:15:19 PM
|