BLD-Final | 2/28/2001 | 3/1/2001 | 3/1/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/28/2001 at 08:59:25. Contact: ###-####. C/C issued. 3/1/2001 12:38:53 PM
|
BLD-Energy code compliance | 11/21/2000 | 11/21/2000 | 11/21/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/21/2000 at 09:31:48. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/16/2000 | 11/16/2000 | 11/16/2000 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/16/2000 at 08:34:19. Contact: ###-####.ok to insulate 11/16/2000 3:53:25 PM
|
BLD-Wall cover | 10/16/2000 | 10/17/2000 | 10/17/2000 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/16/2000 at 16:25:02. Contact: ###-####. Shear OK 10/17/2000 12:32:39 PM
|
BLD-Foundation | 8/18/2000 | 8/18/2000 | 8/18/2000 | P | PASS |
Jim Sly
|
|
|
Ryan ###-####
|
BLD-Footing | 8/15/2000 | 8/15/2000 | 8/15/2000 | P | PART |
Jim Sly
|
|
|
###-#### No approved plans on site 8/16/00 4:59:16 PM
|