BLD-Final | 2/8/2001 | 2/8/2001 | 2/8/2001 | P | PASS |
Jim Sly
|
|
|
###-#### access code 0071 C/C issued 2/8/2001 1:41:44 PM
|
BLD-Wall cover | 11/28/2000 | 11/28/2000 | 11/28/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/28/2000 at 09:06:39. Contact: ###-####. Frame and energy OK 11/28/2000 4:41:43 PM
|
BLD-Framing/Rough-in | 11/27/2000 | 11/27/2000 | 11/27/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/27/2000 at 09:40:28. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/21/2000 | 11/22/2000 | 11/22/2000 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/21/2000 at 10:13:42. Contact: ###-####. Need Mech appr........ 11/22/2000 1:28:20 PM
|
BLD-Framing/Rough-in | 11/1/2000 | 11/1/2000 | 11/1/2000 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/01/2000 at 07:49:09. Contact: ###-####. Shear OK 11/1/2000 2:35:33 PM
|
BLD-Framing/Rough-in | 10/31/2000 | 10/31/2000 | 10/31/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/31/2000 at 11:23:29. Contact: ###-####. Complete prev corr notice. 10/31/2000 1:05:55 PM
|
BLD-Framing/Rough-in | 10/30/2000 | 10/30/2000 | 10/30/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/30/2000 at 09:57:22. Contact: ###-####. C/N...on shear. 10/30/2000 3:30:33 PM
|
BLD-Foundation | 9/27/2000 | 9/27/2000 | 9/27/2000 | P | PART |
Jim Sly
|
|
|
jeremy ###-#### early start
|
BLD-Footing | 9/26/2000 | 9/26/2000 | 9/26/2000 | P | PART |
Jim Sly
|
|
|
Bill ###-####
|