Permanent Occupancy | | 3/6/2001 | 3/6/2001 | | DONE |
|
|
|
|
BLD-Final | 2/9/2001 | 2/9/2001 | 2/9/2001 | A | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 2/9/2001 8:55:49 AM final ok for temp / final ok for perm. upon ele and health dept. sign off.
|
BLD-Final | 2/7/2001 | 2/8/2001 | 2/8/2001 | P | FAIL |
Jim Storey
|
|
|
ALSO FIRE FN--JOHN-- CELL ###-#### need steel banding on duct wrap to ceilling 2 ducts. 2/8/2001 4:28:30 PM
|
FIRE-Final Inspection | 2/8/2001 | 2/8/2001 | 2/8/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 2/8/2001 11:45:23 AM alarms not working; shaft not complete; hood extinguishing not working; need annual sprinkler test 2/8/2001 11:46:25 AM
|
FIRE-Final Inspection | 2/7/2001 | 2/8/2001 | 2/8/2001 | P | PASS |
Rick Jackson
|
|
|
###-#### CELL-- JOHN FIRE FN
|
BLD-Other | 1/25/2001 | 1/26/2001 | 1/26/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/25/2001 at 17:07:26. Contact: ###-####. ceilling ok for cover. 1/26/2001 8:59:54 AM
|
BLD-Framing/Rough-in | 1/8/2001 | 1/9/2001 | 1/9/2001 | P | PART |
Steven Webb
|
|
|
nailing john ###-####. Waiting on final framing until mechanical is approved, sheetrock nailing ok, ok to mud/tape. Ceiling to be accessable for rough in mechanical. 1/9/2001 2:03:14 PM
|
BLD-Framing/Rough-in | 1/4/2001 | 1/5/2001 | 1/5/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/04/2001 at 12:54:40. Contact: ###-####. ok to cover pending plm/mech insp. duct wrap ok is per listed assembly. 1/5/2001 5:34:01 PM
|
BLD-Other | 1/4/2001 | 1/5/2001 | 1/5/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/04/2001 at 12:57:23. Contact: ###-####.
|
BLD-Conference | 1/2/2001 | 1/3/2001 | 1/3/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/02/2001 at 12:13:17. Contact: ###-####.
|
BLD-Conference | 1/2/2001 | 1/3/2001 | 1/3/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/02/2001 at 12:13:17. Contact: ###-####.
|
FIRE-Sprinkler Rough-in | 1/2/2001 | 1/3/2001 | 1/3/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 01/02/2001 at 12:08:54. Contact: ###-####. preliminary inspection on requirements for sprinklers and combustible concealed areas. 1/3/2001 9:16:13 AM
|