Permit Information
Permit NumberBLD00-02980
StatusFinaled
Name SHARIS RESTAURANT
Site Address 2710 W BOISE AVE
Project NameCAPITOL VILLAGE
Customer Number 
ePlanReviewNo
Description
To remodel for a new tenant for use as an assembly occupancy (A-3) restaurant/dining and (B) occupancy kitchen/service/office area in existing 4,895 sq.ft. building per approved plans on file. Work to include miscellaneous interior demolition, new restrooms meeting current accessibility standards, new exterior exit door, new interior walls, interior doors, commercial kitchen with Type I and Type II hoods, fire extinguishing system for Type I hood, interior finish, suspended ceiling work, new walk-in cooler and freezer installations, fire sprinkler work, mechanical work including all new rooftop units and equipment, plumbing work, and electrical work. NOTE: The building is fully fire sprinklered. (P.C.#821-00) JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 3/6/20013/6/2001 DONE
Details
BLD-Final2/9/20012/9/20012/9/2001APASS
DetailsJim Storey
Added by Inspector: 301 On 2/9/2001 8:55:49 AM final ok for temp / final ok for perm. upon ele and health dept. sign off.
BLD-Final2/7/20012/8/20012/8/2001PFAIL
DetailsJim Storey
ALSO FIRE FN--JOHN-- CELL ###-#### need steel banding on duct wrap to ceilling 2 ducts. 2/8/2001 4:28:30 PM
FIRE-Final Inspection2/8/20012/8/20012/8/2001AFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 2/8/2001 11:45:23 AM alarms not working; shaft not complete; hood extinguishing not working; need annual sprinkler test 2/8/2001 11:46:25 AM
FIRE-Final Inspection2/7/20012/8/20012/8/2001PPASS
DetailsRick Jackson
###-#### CELL-- JOHN FIRE FN
BLD-Other1/25/20011/26/20011/26/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/25/2001 at 17:07:26. Contact: ###-####. ceilling ok for cover. 1/26/2001 8:59:54 AM
BLD-Framing/Rough-in1/8/20011/9/20011/9/2001PPART
DetailsSteven Webb
nailing john ###-####. Waiting on final framing until mechanical is approved, sheetrock nailing ok, ok to mud/tape. Ceiling to be accessable for rough in mechanical. 1/9/2001 2:03:14 PM
BLD-Framing/Rough-in1/4/20011/5/20011/5/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/04/2001 at 12:54:40. Contact: ###-####. ok to cover pending plm/mech insp. duct wrap ok is per listed assembly. 1/5/2001 5:34:01 PM
BLD-Other1/4/20011/5/20011/5/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/04/2001 at 12:57:23. Contact: ###-####.
BLD-Conference1/2/20011/3/20011/3/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/02/2001 at 12:13:17. Contact: ###-####.
BLD-Conference1/2/20011/3/20011/3/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/02/2001 at 12:13:17. Contact: ###-####.
FIRE-Sprinkler Rough-in1/2/20011/3/20011/3/2001APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/02/2001 at 12:08:54. Contact: ###-####. preliminary inspection on requirements for sprinklers and combustible concealed areas. 1/3/2001 9:16:13 AM