Permanent Occupancy | | 5/8/2003 | 5/8/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/5/2003 | 5/5/2003 | 5/5/2003 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
BLD-Aging Inspection | 4/21/2003 | 4/21/2003 | 4/21/2003 | | PASS |
Tony Young
|
|
|
|
BLD-Conference | 4/21/2003 | 4/21/2003 | 4/21/2003 | P | PASS |
Tony Young
|
|
|
ok for perm cof o after trades 4/21/2003 2:32:30 PM
|
BLD-Final | 4/21/2003 | 4/21/2003 | 4/21/2003 | P | PASS |
Tony Young
|
|
|
|
BLD-Conference | 2/5/2003 | 2/6/2003 | 2/6/2003 | A | CANC |
Tony Young
|
|
|
cancel per tom moore
|
BLD-Conference | 2/6/2003 | 2/6/2003 | 2/6/2003 | A | PASS |
Tony Young
|
|
|
|
BLD-Final | 2/5/2003 | 2/6/2003 | 2/6/2003 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/05/2003 at 17:25:42. Contact: ###-####.
ok for temp occ. untill trades are ok for perm. occupancy 2/6/2003 2:03:31 PM
|
BLD-Final | 2/5/2003 | 2/5/2003 | 2/5/2003 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/05/2003 at 00:11:04. Contact: ###-####.
|
FIRE-Final Inspection | 2/5/2003 | 2/5/2003 | 2/5/2003 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Millers permission until the curb painting could be done
|
FIRE-Conference | 12/11/2002 | 12/12/2002 | 12/12/2002 | A | DONE |
Troy Cobbley
|
|
|
spoke to the contractor about the painting of the curbing, fire extinguisher locations and the testing of the single station smoke detectors 12/12/2002 4:01:18 PM
|
BLD-Energy code compliance | 7/2/2002 | 7/2/2002 | 7/2/2002 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/02/2002 at 11:17:35. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/28/2002 | 7/1/2002 | 7/1/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/28/2002 at 14:04:32. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/25/2002 | 6/26/2002 | 6/26/2002 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/25/2002 at 11:56:20. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/26/2002 | 6/26/2002 | 6/26/2002 | P | PART |
Tony Young
|
|
|
c/n posted 6/26/2002 2:26:01 PM
|
BLD-Framing/Rough-in | 6/13/2002 | 6/14/2002 | 6/14/2002 | A | NR |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/12/2002 at 18:13:17. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/16/2002 | 5/17/2002 | 5/17/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/16/2002 at 13:41:48. Contact: ###-####.
ext. shear ok 5/17/2002 10:39:40 AM
|
BLD-Framing/Rough-in | 5/2/2002 | 5/3/2002 | 5/3/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/02/2002 at 12:53:48. Contact: ###-####.///off of north street 5/2/2002 1:55:28 PM pre-inspection only, will need a complete inspection , noted some areas of work with contractor . 5/3/2002 6:36:06 PM
|
BLD-Footing | 3/12/2002 | 3/12/2002 | 3/12/2002 | A | DONE |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 3/12/2002 10:27:48 AM
|
BLD-Foundation | 3/12/2002 | 3/12/2002 | 3/12/2002 | A | PASS |
Tony Young
|
|
|
Added by Inspector: 415 On 3/12/2002 10:33:32 AM
|
BLD-Footing | 3/6/2002 | 3/7/2002 | 3/7/2002 | A | PART |
Tony Young
|
|
|
###-####
|
BLD-Footing | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | PART |
Tony Young
|
|
|
3/6/2002 1:07:21 PM
|
BLD-Conference | 3/4/2002 | 3/5/2002 | 3/5/2002 | A | PART |
Tony Young
|
|
|
###-#### TOM ###-####
conf. on changing hds and shear per new engineering///will review, looks ok so far 3/5/2002 9:58:17 AM
|