BLD-Aging Inspection | 12/12/2003 | 12/12/2003 | 12/12/2003 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 7/17/2002 | 7/18/2002 | 7/18/2002 | A | PASS |
Carl Dependahl
|
|
|
WENDEL; Phone #: ###-####; c/n ok, ok for permc/o (L/C). 7/18/2002 11:42:40 AM 7/18/2002 11:43:12 AM
|
BLD-Final | 7/17/2002 | 7/17/2002 | 7/17/2002 | P | NR |
Carl Dependahl
|
|
|
wendell; Phone #: ###-####
|
FIRE-Final Inspection | 7/17/2002 | 7/17/2002 | 7/17/2002 | P | PASS |
Rick Jackson
|
|
|
wendell ###-#### -fire fn
|
BLD-Final | 7/15/2002 | 7/16/2002 | 7/16/2002 | A | NR |
Carl Dependahl
|
|
|
met w/ 409, fire ok 7/16/2002 12:03:16 PM
|
BLD-Final | 7/16/2002 | 7/16/2002 | 7/16/2002 | P | NR |
Carl Dependahl
|
|
|
Wendell ###-####
|
FIRE-Final Inspection | 4/9/2002 | 4/10/2002 | 4/10/2002 | A | FAIL |
Rick Jackson
|
|
|
wendell jones- ###-#### fire fn penetrations; exit signs; audible for alarms not complete 4/10/2002 9:15:25 AM
|
FIRE-Final Inspection | 4/10/2002 | 4/10/2002 | 4/10/2002 | P | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 4/10/2002 9:15:46 AM
|
BLD-Wall cover | 4/5/2002 | 4/8/2002 | 4/8/2002 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 14:49:31. Contact: ###-####.
|
FIRE-Final Inspection | 4/5/2002 | 4/8/2002 | 4/8/2002 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 14:51:12. Contact: ###-####.
|
BLD-Concrete | 3/14/2002 | 3/15/2002 | 3/15/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 3/14/2002 5:09:38 PM wendell ###-#### int concrete at 2hr rated expansion joint system, keep c/n issued w/ BLD00-02375 re joint install, etc. 3/15/2002 11:22:54 AM
|
BLD-Conference | 3/13/2002 | 3/13/2002 | 3/13/2002 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/13/2002 4:40:54 PM re expansion joint firestop system; keep c/n
|
BLD-Final | 3/8/2002 | 3/8/2002 | 3/8/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/8/2002 1:26:18 PM rec'd eng's affidavit/ acceptance...ok; keep c/n re firestops, ok for t/o
|
BLD-Final | 3/7/2002 | 3/7/2002 | 3/7/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/07/2002 at 10:21:31. Contact: ###-####. c/n w/ BLD 01-00234...ok for t/o only. see c/n 3/7/2002 1:58:08 PM
|
FIRE-Final Inspection | 3/7/2002 | 3/7/2002 | 3/7/2002 | A | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 3/7/2002 10:14:09 AM awaiting completion of ground floor corridor 3/7/2002 3:16:14 PM
|
Code Occupancy Approval | | | 3/1/2002 | | PASS |
|
|
|
Inspection noted completion.
|
BLD-Conference | 2/11/2002 | 2/12/2002 | 2/12/2002 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 2/11/2002 2:33:20 PM ###-#### shell, need engs' affidavits; w/ BLD00-02375, add'l "shell" for concrete 2/12/2002 6:12:27 PM
|
BLD-Conference | 2/8/2002 | 2/8/2002 | 2/11/2002 | P | NR |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 2/8/2002 11:31:54 AM ...unable to contact 2/11/2002 2:34:00 PM
|
BLD-Framing/Rough-in | 2/4/2002 | 2/5/2002 | 2/8/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 2/4/2002 4:33:01 PM wendell ###-####...wip, keep c/n, complete firestops; need eng's ok for c/o 2/8/2002 4:38:46 PM
|
BLD-Conference | 2/5/2002 | 2/5/2002 | 2/6/2002 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 2/5/2002 5:57:17 PM wendell ###-####, w/ Ziggy, plbg ok 2/7/2002 9:22:23 AM
|
BLD-Framing/Rough-in | 2/1/2002 | 2/4/2002 | 2/4/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/01/2002 at 16:50:02. Contact: .need all eng's, spec insps ok's; cert of value for modifications req'd 2/4/2002 6:11:21 PM
|
BLD-Conference | 2/1/2002 | 2/1/2002 | 2/1/2002 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/1/2002 4:56:22 PM w/ wendell re resubmittal: canopy, need valuation, add'l spec insp or eng's insp report for framing changes.
|
BLD-Framing/Rough-in | 2/1/2002 | 2/1/2002 | 2/1/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/1/2002 4:58:42 PM shell...canopy only, need eng's verifications as built.
|
BLD-Conference | 1/29/2002 | 1/29/2002 | 1/29/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 1/29/2002 12:38:05 PM w/ Wendall...need canopy plans 1/29/2002 6:14:30 PM
|
BLD-Conference | 1/3/2002 | 1/3/2002 | 1/3/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/3/2002 3:30:12 PM need approvals by all agencies for temp use...will have profit mtg.
|
BLD-Aging Inspection | 12/31/2001 | 12/31/2001 | 12/31/2001 | | NR |
Carl Dependahl
|
|
|
NICU shell only, wip. 12/31/2001 1:22:59 PM
|
BLD-Aging Inspection | 10/29/2001 | 10/29/2001 | 11/5/2001 | | NR |
Carl Dependahl
|
|
|
shell only, Nicu phase 2; wip 11/5/2001 12:05:29 PM
|
BLD-Aging Inspection | 8/27/2001 | 8/27/2001 | 8/27/2001 | | PART |
Carl Dependahl
|
|
|
St Lukes East tower/ NICU; wip 8/27/2001 11:35:53 AM
|
BLD-Conference | 8/27/2001 | 8/27/2001 | 8/27/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/27/2001 11:30:10 AM w/ Wendall onsite. wip, receiving spec insp reports.
|
BLD-Conference | 6/26/2001 | 6/26/2001 | 6/26/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/26/2001 11:31:21 AM onsite w/ Wendall & framer
|
BLD-Framing/Rough-in | 6/25/2001 | 6/25/2001 | 6/25/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/25/2001 9:26:36 AM ok to pre-rock at shafts...back of elec chase, along north stair, call for insps when ready.
|
BLD-Framing/Rough-in | 6/14/2001 | 6/14/2001 | 6/14/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/14/2001 8:46:59 AM shafts at ground level...fasten edges of core bd. at non-c-h studs/corners; wip ok to continue.
|
BLD-Aging Inspection | 6/4/2001 | 6/4/2001 | 6/4/2001 | | PASS |
Carl Dependahl
|
|
|
wip...recvg spec insp reports,deck & col's being placed 6/4/2001 9:55:54 AM
|
BLD-Concrete | 6/4/2001 | 6/4/2001 | 6/4/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/4/2001 3:24:54 PM part, pend spec insp.
|