BLD-Final | 3/6/2001 | 3/7/2001 | 3/7/2001 | P | PASS |
Steven Webb
|
|
|
###-####LC #20122 issued, outside grading not completed at time of inspection due to winter time conditions. 3/7/2001 3:43:12 PM
|
BLD-Final | 1/30/2001 | 1/31/2001 | 1/31/2001 | A | CANC |
Steven Webb
|
|
|
###-#### cancel by contractor
1/31/2001 10:01:27 AM
|
BLD-Energy code compliance | 1/26/2001 | 1/29/2001 | 1/29/2001 | P | PASS |
Steven Webb
|
|
|
holton homes ###-#### ok to cover 1/29/2001 1:43:22 PM
|
BLD-Framing/Rough-in | 1/26/2001 | 1/26/2001 | 1/26/2001 | P | PASS |
Steven Webb
|
|
|
fr george- ###-#### -re-insp ok to insulate 1/26/2001 11:51:34 AM
|
BLD-Framing/Rough-in | 1/23/2001 | 1/24/2001 | 1/24/2001 | A | PASS |
Steven Webb
|
|
|
###-####\\nailing ok to side 1/24/2001 11:31:58 AM
|
BLD-Framing/Rough-in | 1/23/2001 | 1/24/2001 | 1/24/2001 | P | FAIL |
Tom Arcoraci
|
|
|
cn issued 1/24/2001 3:35:10 PM
|
BLD-Framing/Rough-in | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | NR |
Steven Webb
|
|
|
###-####: not ready, prior c/n items from inspector 408 are not completed. 1/24/2001 4:06:16 PM
|
BLD-Framing/Rough-in | 1/22/2001 | 1/23/2001 | 1/23/2001 | A | FAIL |
Steven Webb
|
|
|
shear nail George ###-#### c/n issued--1) additional nailing required throughout, 2) fastening required above hd 3) south wall need additional osb not insulation board per plans. 1/23/2001 11:32:34 AM
|
BLD-Framing/Rough-in | 1/19/2001 | 1/19/2001 | 1/19/2001 | P | NR |
Steven Webb
|
|
|
shear nailing george ###-#### No approved plans on site 1/19/2001 2:29:58 PM
|
BLD-Foundation | 12/27/2000 | 12/28/2000 | 12/28/2000 | A | PART |
Steven Webb
|
|
|
###-####: holdowns not installed at time of inspection. 12/28/2000 11:09:09 AM
|
BLD-Footing | 12/27/2000 | 12/27/2000 | 12/27/2000 | P | PART |
Steven Webb
|
|
|
###-#### set backs ok, all steel not in place. 12/27/2000 3:20:48 PM
|