BLD-Final | 3/26/2001 | 3/26/2001 | 3/26/2001 | A | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/26/2001 at 07:10:01. Contact: ###-####.No access 3/26/2001 10:03:57 AM
|
BLD-Final | 3/26/2001 | 3/26/2001 | 3/26/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/26/2001 at 10:47:56. Contact: ###-####.C. of C. #21412 issued 3/26/2001 3:12:52 PM
|
BLD-Final | 3/26/2001 | 3/26/2001 | 3/26/2001 | P | PASS |
Steven Webb
|
|
|
Added by Inspector: 420 On 3/26/2001 3:13:12 PM
|
BLD-Final | 3/23/2001 | 3/23/2001 | 3/23/2001 | P | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/23/2001 at 11:19:22. Contact: ###-####.C/n --rim joist needs insulated, landscape, 3/23/2001 1:15:15 PM
|
BLD-Energy code compliance | 2/13/2001 | 2/13/2001 | 2/13/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 02/13/2001 at 10:00:29. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/12/2001 | 2/12/2001 | 2/12/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 02/12/2001 at 07:24:15. Contact: ###-####.ok to insulate. 2/12/2001 8:56:17 AM
|
BLD-Framing/Rough-in | 2/8/2001 | 2/9/2001 | 2/9/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 11:16:32. Contact: ###-####. c/n issued--Header at fp not per plans, Top plate straps needed on header in d. room, Damaged floor joist in crawl needs engineering or replaced, Overbuild roof at garage needs solid bearing for uprights---ok to insulate. 2/9/2001 11:51:19 AM
|
BLD-Framing/Rough-in | 1/31/2001 | 1/31/2001 | 1/31/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/31/2001 at 07:21:46. Contact: ###-####. Shear--ok to side 1/31/2001 9:48:46 AM
|
BLD-Framing/Rough-in | 1/30/2001 | 1/30/2001 | 1/30/2001 | A | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/30/2001 at 06:56:21. Contact: ###-####. c/n issued, additional nailing required plus non-shear panels are required to have at least 20% fastened. 1/30/2001 12:58:26 PM
|
BLD-Foundation | 12/28/2000 | 12/29/2000 | 12/29/2000 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 12/28/2000 at 16:46:34. Contact: ###-####. Part rebar in place, hd not installed at time of inspection 12/29/2000 10:53:46 AM
|
BLD-Footing | 12/28/2000 | 12/28/2000 | 12/28/2000 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 12/28/2000 at 10:23:43. Contact: ###-####. Steel not installed at time of inspection. 12/28/2000 3:38:17 PM
|