BLD-Final | 4/16/2001 | 4/17/2001 | 4/17/2001 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/16/2001 at 10:50:00. Contact: ###-####.
|
Permanent Occupancy | | 4/17/2001 | 4/17/2001 | | DONE |
|
|
|
|
BLD-Final | 4/16/2001 | 4/16/2001 | 4/16/2001 | P | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/16/2001 at 10:50:46. Contact: ###-####.
|
BLD-Final | 4/11/2001 | 4/11/2001 | 4/11/2001 | P | FAIL |
Carl Dependahl
|
|
|
buck ###-####; c/n signage, handrail, other final; fire insp onsite...pendi 4/11/2001 3:31:44 PM ng his ok for t/o 4/11/2001 3:31:56 PM
|
FIRE-Final Inspection | 4/11/2001 | 4/11/2001 | 4/11/2001 | P | PASS |
Rick Jackson
|
|
|
Buck ###-####
|
BLD-Conference | 3/15/2001 | 3/15/2001 | 3/15/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/15/2001 5:00:55 PM w/ ziggy re plbg ok
|
BLD-Framing/Rough-in | 3/8/2001 | 3/8/2001 | 3/8/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/8/2001 4:34:09 PM restroom lids ok, wood removed, gyp added as req'd...int walls ok, may need dampers at hvac at demising
|
BLD-Conference | 3/7/2001 | 3/7/2001 | 3/7/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/7/2001 12:36:29 PM verbal c/n re use of f.r.t.plywood...must be encapsulated w/i assy or continuously backed by non-comb. surface at II_1hr
|