BLD-Final | 6/8/2001 | 6/8/2001 | 6/8/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/08/2001 at 08:57:36. Contact: ###-####.
|
BLD-Final | 5/31/2001 | 6/1/2001 | 6/1/2001 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/31/2001 at 16:43:47. Contact: ###-####.c/n posted 6/1/2001 2:51:05 PM
|
BLD-Aging Inspection | 5/16/2001 | 5/16/2001 | 5/16/2001 | | CANC |
Tony Young
|
|
|
This is an aging activity,ok 5/16/2001 8:28:16 AM
|
BLD-Energy code compliance | 3/14/2001 | 3/14/2001 | 3/14/2001 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/14/2001 at 07:08:54. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/12/2001 | 3/13/2001 | 3/13/2001 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 14:21:28. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/6/2001 | 3/7/2001 | 3/7/2001 | A | PART |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 3/6/2001 11:13:38 AM shear
ext. shear ok 3/7/2001 11:43:03 AM
|
BLD-Framing/Rough-in | 3/5/2001 | 3/6/2001 | 3/6/2001 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/05/2001 at 17:06:55. Contact: ###-####.
not ready 3/6/2001 11:13:11 AM
|
BLD-Foundation | 1/24/2001 | 1/25/2001 | 1/25/2001 | A | PART |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 1/24/2001 3:18:21 PM
garage found. wip, ok w/ verbal corrctions 1/25/2001 9:46:01 AM
|
BLD-Foundation | 1/23/2001 | 1/24/2001 | 1/24/2001 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 01/23/2001 at 17:24:59. Contact: ###-####.
|
BLD-Concrete | 1/22/2001 | 1/23/2001 | 1/23/2001 | A | CANC |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 1/22/2001 12:59:27 PM garage
|
BLD-Footing | 1/22/2001 | 1/23/2001 | 1/23/2001 | A | PART |
Tony Young
|
|
|
Jeremy ###-####
wip, ok w/ verbal corrections 1/23/2001 10:36:03 AM
|
BLD-Footing | 1/21/2001 | 1/22/2001 | 1/22/2001 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/21/2001 at 18:21:36. Contact: ###-####.
|
BLD-Footing | 1/22/2001 | 1/22/2001 | 1/22/2001 | P | NR |
Tony Young
|
|
|
|
BLD-Footing | 1/19/2001 | 1/19/2001 | 1/19/2001 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 01/19/2001 at 07:10:16. Contact: ###-####.
|
BLD-Foundation | 1/12/2001 | 1/16/2001 | 1/16/2001 | P | PART |
Tony Young
|
|
|
Jeremy ###-####
all ready poured, looks ok 1/17/2001 8:39:40 AM
|
BLD-Footing | 1/11/2001 | 1/11/2001 | 1/11/2001 | P | PART |
Tony Young
|
|
|
JEREMY ###-#### FT
wip, ok so far 1/11/2001 3:55:21 PM
|