BLD-Final | 11/30/2001 | 11/30/2001 | 11/30/2001 | A | CANC |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 11/30/2001 9:54:52 AM wrong permit number given by contractor. 11/30/2001 9:58:11 AM
|
BLD-Final | 9/24/2001 | 9/24/2001 | 9/24/2001 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 9/6/2001 | 9/7/2001 | 9/7/2001 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/06/2001 at 11:40:27. Contact: ###-####. Temp Occ.......... Need all req signatures for perm occ. 9/7/2001 1:07:23 PM 9/7/2001 1:09:46 PM
|
FIRE-Final Inspection | 9/6/2001 | 9/7/2001 | 9/7/2001 | A | PASS |
Joe Tawney
|
|
|
REinsp OK for certificate of completion 9/7/2001 10:18:44 AM
|
BLD-Final | 9/4/2001 | 9/5/2001 | 9/5/2001 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/04/2001 at 07:29:50. Contact: ###-####.
|
FIRE-Final Inspection | 9/4/2001 | 9/5/2001 | 9/5/2001 | A | FAIL |
Joe Tawney
|
|
|
REinsp Fail 9/5/2001 10:41:27 AM
|
FIRE-Final Inspection | 8/31/2001 | 9/4/2001 | 9/4/2001 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/31/2001 at 08:57:03. Contact: ###-####. will reshedule; 409 ran out of time 9/4/2001 3:20:17 PM
|
BLD-Final | 8/29/2001 | 8/31/2001 | 8/31/2001 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/29/2001 at 14:52:29. Contact: ###-####. Need signatures 8/31/2001 4:32:33 PM
|
FIRE-Final Inspection | 8/28/2001 | 8/30/2001 | 8/30/2001 | P | FAIL |
Joe Tawney
|
|
|
Reinsp Fail Gen test and door seals, closers, ^& astrigals. sign for location of all AHU 8/30/2001 5:10:18 PM
|
FIRE-Final Inspection | 8/24/2001 | 8/27/2001 | 8/27/2001 | P | FAIL |
Joe Tawney
|
|
|
Final Fail C/N issued 8/27/2001 4:17:53 PM
|
BLD-Conference | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | PART |
Jim Sly
|
|
|
Checked firestop joint spray and rejected. 8/24/2001 5:49:39 PM
|
FIRE-Final Inspection | 8/22/2001 | 8/23/2001 | 8/23/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### greg
|
FIRE-Final Inspection | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | FAIL |
Joe Tawney
|
|
|
Final Fail Spklr and alarms failed 8/21/2001 3:42:35 PM
|
BLD-Conference | 8/13/2001 | 8/14/2001 | 8/14/2001 | A | PART |
Jim Sly
|
|
|
###-#### greg Reveiwed all prev corr notices with new Superint (Greg). 8/14/2001 11:26:16 AM
|
FIRE-Conference | 8/10/2001 | 8/13/2001 | 8/13/2001 | A | CANC |
Joe Tawney
|
|
|
To be rescheduled 8/13/2001 9:38:34 AM
|
FIRE-Conference | 7/13/2001 | 7/16/2001 | 7/16/2001 | A | PASS |
Joe Tawney
|
|
|
Conf on installing shelving before blding is signed off. I stated OKI . 7/16/2001 2:37:47 PM
|
BLD-Conference | 7/12/2001 | 7/13/2001 | 7/13/2001 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 09:58:45. Contact: ###-####. C/N posted.... Discussed issue of No work beyond scope of work for shell and core....Need Permit for Target store Occupancy. 7/13/2001 10:19:17 AM
|
BLD-Conference | 7/12/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 07:33:58. Contact: ###-####.
|
BLD-Conference | 7/9/2001 | 7/10/2001 | 7/10/2001 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/09/2001 at 13:52:33. Contact: ###-####. PROFIT Meeting....Need New permit for Target Occ. Need final letter of appr from Eng. and special insp Agency. Separate permits Req for other Occ. Insp of rated shaft Req. 7/10/2001 9:23:22 AM
|
BLD-Conference | 7/5/2001 | 7/6/2001 | 7/6/2001 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/05/2001 at 09:10:25. Contact: ###-####. North 1/2 main floor Ceiling grid......OK. 7/6/2001 9:44:55 AM
|
BLD-Conference | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/02/2001 at 08:01:22. Contact: ###-####. Grid ceiling OK.....South 1/2 only....will spot check for spacer bars after tiles installed. 7/2/2001 3:57:57 PM
|
BLD-Conference | 6/28/2001 | 6/29/2001 | 6/29/2001 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/28/2001 at 09:59:54. Contact: ###-####. Ceiling grid. 6/29/2001 10:45:41 AM
|
BLD-Framing/Rough-in | 6/1/2001 | 6/4/2001 | 6/4/2001 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/01/2001 at 09:08:33. Contact: . All framing OK Pend Plumb approval.....(verify). 6/4/2001 4:08:59 PM
|
BLD-Framing/Rough-in | 5/14/2001 | 5/14/2001 | 5/14/2001 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/14/2001 at 06:33:51. Contact: ###-####. OK to cover Rear corridor and East wall. 5/14/2001 1:18:23 PM
|
BLD-Framing/Rough-in | 5/9/2001 | 5/9/2001 | 5/9/2001 | P | PART |
Jim Sly
|
|
|
two exterior colums\\###-#### OK to cover (rear) Corridor and Long North to South wall ....1 side only. 5/9/2001 5:39:38 PM
|
BLD-Footing | 3/26/2001 | 3/26/2001 | 3/26/2001 | P | PART |
Jim Sly
|
|
|
###-####
|
BLD-Footing | 3/23/2001 | 3/23/2001 | 3/23/2001 | P | PART |
Jim Sly
|
|
|
###-#### Footing at N. and E. wall....Pending special insp and appr. 3/23/2001 2:14:14 PM
|
BLD-Footing | 3/21/2001 | 3/21/2001 | 3/21/2001 | P | PART |
Jim Sly
|
|
|
###-#### W & N footing pending special insp and appr. 3/21/2001 4:10:48 PM
|
BLD-Footing | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | PART |
Jim Sly
|
|
|
###-#### Footing at South and part of East wall....starting CMU....Pending special insp and approval.
3/20/2001 3:35:42 PM 3/20/2001 3:37:01 PM
|
BLD-Footing | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | PART |
Carl Dependahl
|
|
|
###-####
|