BLD-Final | 9/5/2001 | 9/6/2001 | 9/6/2001 | A | PASS |
Tony Young
|
|
|
###-####
|
FIRE-Final Inspection | 8/28/2001 | 8/28/2001 | 8/28/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/28/2001 1:14:47 PM
|
BLD-Final | 7/27/2001 | 7/30/2001 | 7/30/2001 | A | FAIL |
Tony Young
|
|
|
dave ###-#### fire is also going out
need trade sign offs, no inspection made 7/30/2001 10:41:58 AM
|
FIRE-Final Inspection | 7/27/2001 | 7/30/2001 | 7/30/2001 | A | FAIL |
Rick Jackson
|
|
|
Dave ###-#### lobby doors not latching due to positve pressure; penetrations; detector for doors with hold-opens 7/30/2001 9:16:09 AM
|
BLD-Aging Inspection | 6/27/2001 | 6/27/2001 | 6/27/2001 | | PASS |
Tony Young
|
|
|
active 6/27/2001 10:18:33 AM
|
BLD-Framing/Rough-in | 4/26/2001 | 4/27/2001 | 4/27/2001 | A | PART |
Tony Young
|
|
|
ken ###-#### fr -fire corridor upgrade
c/n made ok except still need clarification of S frames, last item of correction, ok to put ceiling tile in. 4/27/2001 11:55:43 AM
|
BLD-Framing/Rough-in | 4/24/2001 | 4/24/2001 | 4/24/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/24/2001 5:47:30 PM c/n, seal- firestop gaps,clarify door upgrade extent, etc, ok to tape & patch...add fasteners at top of tunnels, other insp this date in error. 4/24/2001 5:48:28 PM
|
BLD-Framing/Rough-in | 4/23/2001 | 4/24/2001 | 4/24/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-####; c/n, add seismic pod, obtain cdhd final. ok for t/o 4/24/2001 4:58:13 PM
|
FIRE-Final Inspection | 4/23/2001 | 4/24/2001 | 4/24/2001 | A | FAIL |
Rick Jackson
|
|
|
###-#### KEN not a final inspection - checked coddidor walls and sprinklers - okay; will recheck some penetrations on final 4/24/2001 2:31:01 PM
|