To construct a 1647 sq. ft. two story single family dwelling (848 sq. ft. first floor/799 sq. ft. second floor) with a 114 sq. ft. covered front porch. A DETACHED 480 sq. ft. two car garage with a 480 sq. ft. bonus room above to be constructed in the rear of the property. Per approved plans and requirement list. PC#060 (SAM)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/23/20017/25/20017/25/2001APASS
DetailsDave Hannah
Wendy ###-####
BLD-Energy code compliance6/11/20016/11/20016/11/2001PPASS
DetailsCarl Dependahl
###-####
BLD-Framing/Rough-in6/11/20016/11/20016/11/2001PPASS
DetailsCarl Dependahl
BLD-Energy code compliance6/6/20016/7/20016/7/2001APART
DetailsDave Hannah
###-#### OR ###-#### WENDY seal package 6/7/2001 11:56:57 AM
BLD-Framing/Rough-in6/6/20016/7/20016/7/2001APASS
DetailsDave Hannah
ok to insulate 6/7/2001 11:57:20 AM
BLD-Conference5/21/20015/21/20015/21/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 5/21/2001 2:43:05 PM w/ owner, ext shear ok...chk plans.
BLD-Framing/Rough-in5/16/20015/18/20015/18/2001PPART
DetailsCarl Dependahl
shear on gar -wendy-- ###-#### ...may req int osb at gar door... 5/18/2001 5:02:33 PM
BLD-Framing/Rough-in5/15/20015/15/20015/15/2001PPART
DetailsTony Young
shear on house, exterior shear ok w/ verbal corrections, still need to see int. shear on house and garage shear later 5/15/2001 2:37:24 PM
BLD-Footing4/27/20014/30/20014/30/2001APART
DetailsTony Young
###-#### garage ftg w.i.p. 4/30/2001 9:34:18 AM
BLD-Foundation4/24/20014/25/20014/25/2001APART
DetailsCarl Dependahl
###-####, awaiting eng's letter...steel in place pour at own risk, looks ok 4/25/2001 9:52:53 AM 4/25/2001 9:53:37 AM
BLD-Footing4/23/20014/23/20014/23/2001PPART
DetailsCarl Dependahl
###-####; pour at own risk, need eng's formal statement for soils...has MTI's written report & recommendation, follow up w/ stamped letter 4/23/2001 4:46:14 PM
BLD-Conference3/20/20013/21/20013/21/2001AFAIL
DetailsTom Arcoraci
###-#### Wendy 11:30 need soil eng to ok soil for footigs 3/21/2001 12:07:16 PM