BLD-Final | 8/14/2001 | 8/14/2001 | 8/14/2001 | A | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 8/14/2001 11:51:57 AM Reinsp Ok for certificate of completion
|
BLD-Final | 8/8/2001 | 8/10/2001 | 8/10/2001 | A | PART |
Tony Young
|
|
|
call first ###-####
temp. occ. ok pending other trades, then perm. occ. ok pending trades 8/10/2001 10:21:53 AM
|
FIRE-Final Inspection | 8/8/2001 | 8/10/2001 | 8/10/2001 | A | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail Fire ext and possible alarm submittal 8/10/2001 10:33:37 AM
|
BLD-Aging Inspection | 7/17/2001 | 7/17/2001 | 7/17/2001 | | PART |
Tony Young
|
|
|
wip 7/17/2001 8:59:11 AM
|
BLD-Concrete | 5/17/2001 | 5/17/2001 | 5/17/2001 | P | PART |
Tony Young
|
|
|
wip, ok to grout, ok to go 6ft on fuel tank wall 5/17/2001 3:54:47 PM
|
BLD-Foundation | 5/17/2001 | 5/17/2001 | 5/17/2001 | P | FAIL |
Tony Young
|
|
|
masonry wall Curtis ###-####
|
BLD-Concrete | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | PART |
Tony Young
|
|
|
masonary ###-####
ok to grout 4 ' lift on gen room, 12' high now 5/16/2001 2:24:26 PM
|
BLD-Concrete | 5/14/2001 | 5/15/2001 | 5/15/2001 | A | PART |
Tony Young
|
|
|
###-#### late am
|
BLD-Framing/Rough-in | 5/11/2001 | 5/14/2001 | 5/14/2001 | P | PART |
Tony Young
|
|
|
masonary wall ###-####,bond beam ok w/ verbal corrections 5/15/2001 9:10:47 AM
|
BLD-Footing | 4/30/2001 | 5/1/2001 | 5/1/2001 | A | PART |
Tony Young
|
|
|
###-####
|
BLD-Foundation | 4/20/2001 | 4/23/2001 | 4/23/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/20/2001 at 14:17:52. Contact: .
verbal corrections 4/23/2001 10:02:26 AM
|
BLD-Footing | 4/18/2001 | 4/19/2001 | 4/19/2001 | A | PASS |
Dave Hannah
|
|
|
Vern ###-####
|