BLD-Conference | 8/15/2002 | 8/15/2002 | 8/15/2002 | A | CANC |
Russ Owen
|
|
|
|
BLD-Framing/Rough-in | 1/1/2002 | 1/1/2002 | 1/1/2002 | P | PART |
Russ Owen
|
|
|
Added by Inspector: 407 On 1/1/2002 2:23:54 PM went over s-i requirements again,will need to have some items noted on plans inspected,lower floor walls in eye glass shop have been cover with drywall w-o approval, appears ok noted contractor to submit change order from architect for shat wall at duct through floor contact at job site is Frank.
|
BLD-Framing/Rough-in | 12/12/2001 | 12/13/2001 | 12/13/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/12/2001 at 20:30:12. Contact: ###-####.ok perm oc all signatures on card. 12/13/2001 11:52:39 AM
|
FIRE-Final Inspection | 12/12/2001 | 12/13/2001 | 12/13/2001 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 12/13/2001 7:42:08 AM
|
Permanent Occupancy | | 12/13/2001 | 12/13/2001 | | DONE |
|
|
|
|
BLD-Final | 12/6/2001 | 12/7/2001 | 12/7/2001 | A | NR |
Russ Owen
|
|
|
###-#### FRANK. needs F L S inspection.. 12/7/2001 11:54:40 AM
|
FIRE-Final Inspection | 12/6/2001 | 12/7/2001 | 12/7/2001 | A | FAIL |
Troy Cobbley
|
|
|
Emergency lights and exit signs would not operate. Inspection to be rescheduled 12/7/2001 8:29:56 AM
|
BLD-Final | 12/5/2001 | 12/6/2001 | 12/6/2001 | A | PART |
Russ Owen
|
|
|
###-#### FRANK . needs fire/life insp. 12/6/2001 12:21:56 PM
|
FIRE-Final Inspection | 12/5/2001 | 12/6/2001 | 12/6/2001 | A | FAIL |
Troy Cobbley
|
|
|
exit signs and emergency lights need to be tested. fire extinguishers ok 12/6/2001 2:05:21 PM
|
BLD-Framing/Rough-in | 12/4/2001 | 12/4/2001 | 12/4/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/04/2001 at 06:44:47. Contact: ###-####. 12/4/2001 4:00:53 PM.went over items for final. 12/4/2001 4:01:20 PM
|
BLD-Framing/Rough-in | 11/15/2001 | 11/15/2001 | 11/15/2001 | A | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 10/19/2001 | 10/22/2001 | 10/22/2001 | A | NR |
Russ Owen
|
|
|
FRANK ###-####
|
BLD-Framing/Rough-in | 10/18/2001 | 10/19/2001 | 10/19/2001 | P | CANC |
Carl Dependahl
|
|
|
###-#### frank FRANK CALLED IN TO CANCEL INSPECTION AND RSET FOR MONDAY 10-19-01 ///DLD
|
FIRE-Final Inspection | 10/18/2001 | 10/19/2001 | 10/19/2001 | P | CANC |
Carl Dependahl
|
|
|
###-#### frank 10-19-01 FRANK CALLED IN TO CANCEL THIS INSPECTION..
|
BLD-Framing/Rough-in | 10/4/2001 | 10/4/2001 | 10/4/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/04/2001 at 06:10:33. Contact: ###-####. went over req for final with contractor. 10/4/2001 11:54:11 AM
|
BLD-Final | 10/3/2001 | 10/3/2001 | 10/3/2001 | P | PART |
Russ Owen
|
|
|
###-#### frank . This is fod 10/4/2001 11:52:56 AM the racking permit. 10/4/2001 11:53:08 AM
|
BLD-Framing/Rough-in | 9/18/2001 | 9/19/2001 | 9/19/2001 | A | PART |
Russ Owen
|
|
|
frank ###-#### fr. Need to firestop the top of auto dept 1 hr wall and new chase through floor. along with new rated access door. 9/19/2001 12:25:51 PM
|
BLD-Framing/Rough-in | 8/28/2001 | 8/28/2001 | 8/28/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/28/2001 at 06:00:00. Contact: ###-####.upper and lower roll down doors ok to cover. 8/28/2001 11:50:29 AM
|
BLD-Framing/Rough-in | 8/23/2001 | 8/23/2001 | 8/23/2001 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/23/2001 at 06:32:18. Contact: ###-####. add'l c/n, add fasteners, braces track, etc. recall. 8/23/2001 11:51:49 AM
|
BLD-Framing/Rough-in | 8/14/2001 | 8/15/2001 | 8/15/2001 | A | CANC |
Tom Arcoraci
|
|
|
pager ###-#### eric... please page eric before.
|
BLD-Framing/Rough-in | 8/13/2001 | 8/14/2001 | 8/14/2001 | A | FAIL |
Russ Owen
|
|
|
###-#### pager frank. New front roll up doors,c/n bulk head not sealed as sheetrock has been removed also framing not per plan left c/n to have architect verify if bulk heads need to be complete for smoke evac system and provide framing approval for as built. 8/14/2001 1:38:49 PM
|
BLD-Framing/Rough-in | 8/6/2001 | 8/6/2001 | 8/6/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/06/2001 at 06:11:42. Contact: ###-####.lower floor wall, needs top braced. 8/6/2001 2:55:47 PM
|
BLD-Framing/Rough-in | 7/31/2001 | 7/31/2001 | 7/31/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/31/2001 at 00:54:34. Contact: ###-####. tall wall lower floor ok to sheetrock,noticed existing lights not supported in t-bar grid ceiling, contractor is going to wire support. 7/31/2001 10:11:22 AM
|
BLD-Framing/Rough-in | 6/6/2001 | 6/7/2001 | 6/7/2001 | A | FAIL |
Russ Owen
|
|
|
ceiling grid ###-#### need to repair fire proofing,2 lights need ties, wall needs to be braced, area of customer pic up./7/2002 11:49:57 AM ir 1/7/2002 11:50:02 AM 1/7/2002 11:50:59 AM
|
BLD-Framing/Rough-in | 5/31/2001 | 6/1/2001 | 6/1/2001 | A | PART |
Tom Arcoraci
|
|
|
ceiling frank ###-#### DONE BY 407 6/1/2001 1:45:30 PM
|
BLD-Framing/Rough-in | 5/2/2001 | 5/3/2001 | 5/3/2001 | A | PART |
Russ Owen
|
|
|
ceiling Frank ###-#### fire stoping in firewall at auto repair area not done also lights not wire supported in adjoing roo also grid ceiling in 3 areas marked on c/n posted on job trailer, not complete. lower floor grid ok to cover, pending all other required insp. also went over special inspection requirements with Frank job supper. will be contacting approved agency asap. 12/3/2001 1:19:20 PM
|
BLD-Framing/Rough-in | 4/30/2001 | 5/1/2001 | 5/1/2001 | A | NH |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/30/2001 at 10:22:01. Contact: ###-####. unable to locate contractor. left message to call me. 12/2/2001 2:55:37 PM
|
BLD-Other | 4/11/2001 | 4/12/2001 | 4/12/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/11/2001 at 16:57:26. Contact: ###-####.front column at repair entrance, removed suport post for stair landing replaced with angle supported at top,as per plans. 4/12/2001 10:46:15 AM
|
BLD-Footing | 4/3/2001 | 4/4/2001 | 4/4/2001 | A | PART |
Russ Owen
|
|
|
Frank ###-#### interior wall 1 firewall also c/n posted in job trailer with ,jom mgr. 4/4/2001 1:45:10 PM
|
BLD-Framing/Rough-in | 4/3/2001 | 4/4/2001 | 4/4/2001 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/03/2001 at 16:28:29. Contact: ###-####...recall 4/5/2001 11:00:39 AM
|
BLD-Framing/Rough-in | 3/28/2001 | 3/30/2001 | 3/29/2001 | P | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/28/2001 at 13:30:26. Contact: ###-####.
|