BLD-Final | 6/26/2001 | 6/27/2001 | 6/27/2001 | A | PASS |
Steven Webb
|
|
|
###-#### C. of C. #20441 issued. Inspection performed on 6/26/01. 6/26/2001 1:31:29 PM
|
BLD-Final | 6/25/2001 | 6/26/2001 | 6/26/2001 | A | FAIL |
Tony Young
|
|
|
Pat ###-#### no access due to wet floors, also rear stairs are not done, rear landing not 36" ,no other inspection made 6/26/2001 11:45:11 AM
|
BLD-Final | 6/19/2001 | 6/20/2001 | 6/20/2001 | P | FAIL |
Steven Webb
|
|
|
Pat ###-#### C/N posted on site 6/20/2001 2:02:34 PM
|
BLD-Conference | 4/30/2001 | 4/30/2001 | 4/30/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/30/2001 at 11:20:54. Contact: ###-####.
|
BLD-Energy code compliance | 4/30/2001 | 4/30/2001 | 4/30/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/30/2001 at 11:20:25. Contact: ###-####...has TJI eng'g onsite, ok to cover per 420 4/30/2001 3:48:43 PM
|
BLD-Energy code compliance | 4/27/2001 | 4/27/2001 | 4/27/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/27/2001 at 07:15:01. Contact: ###-####.
c/n posted, ok to sheetrock unaffected areas 4/27/2001 10:34:40 AM
|
BLD-Conference | 4/26/2001 | 4/26/2001 | 4/26/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/26/2001 at 11:24:48. Contact: ###-####.
|
BLD-Energy code compliance | 4/26/2001 | 4/26/2001 | 4/26/2001 | P | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/26/2001 at 11:23:56. Contact: ###-####. Cancelled by contractor. 4/26/2001 2:20:59 PM
|
BLD-Framing/Rough-in | 4/17/2001 | 4/17/2001 | 4/17/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/17/2001 at 07:21:24. Contact: ###-####. C/N posted-ok to insulate 4/17/2001 9:43:54 AM
|
BLD-Framing/Rough-in | 4/16/2001 | 4/16/2001 | 4/16/2001 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/16/2001 at 10:17:30. Contact: ###-####. C/N issued-ok to insulate. 4/16/2001 1:55:30 PM
|
BLD-Framing/Rough-in | 4/13/2001 | 4/13/2001 | 4/13/2001 | P | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/13/2001 at 11:16:57. Contact: ###-####.C/N issued-Need truss layout with hanger schedule plus mechanical r.i prior to inspection. 4/13/2001 3:03:34 PM
|
BLD-Framing/Rough-in | 4/10/2001 | 4/10/2001 | 4/10/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/10/2001 at 11:25:26. Contact: ###-####. SHEAR---Prior c/n item corrected. 4/10/2001 3:45:11 PM
|
BLD-Framing/Rough-in | 4/6/2001 | 4/6/2001 | 4/6/2001 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/06/2001 at 11:08:06. Contact: ###-####. C/n issued-missing hd nw side of front--ok to side-provide eng. or retrofit hd with equiv. uplift capabilties. 4/6/2001 2:26:35 PM
|
BLD-Foundation | 2/28/2001 | 2/28/2001 | 2/28/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 02/28/2001 at 07:21:24. Contact: ###-####. wip--rebar ok 2/28/2001 11:42:32 AM
|
BLD-Footing | 2/26/2001 | 2/27/2001 | 2/27/2001 | A | PASS |
Tom Arcoraci
|
|
|
Rob ###-####
|
BLD-Footing | 2/26/2001 | 2/26/2001 | 2/26/2001 | P | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 02/26/2001 at 10:58:23. Contact: ###-####.Excavation only being done, wip. 2/26/2001 2:41:49 PM
|