BLD-Final | 6/22/2001 | 6/25/2001 | 6/25/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/22/2001 at 21:16:06. Contact: ###-####. ok perm oc. 6/25/2001 9:46:39 AM
|
FIRE-Final Inspection | 6/22/2001 | 6/25/2001 | 6/25/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/22/2001 at 21:15:27. Contact: ###-####.
|
Permanent Occupancy | | 6/25/2001 | 6/25/2001 | | DONE |
|
|
|
|
BLD-Other | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/20/2001 at 13:47:34. Contact: ###-####. need wire support at left rear areamain runner closest to rear wall ,more than 4 foot span. wil check at final. 1/21/2002 11:06:41 AM
|
FIRE-Sprinkler Rough-in | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | PART |
Joe Tawney
|
|
|
OK on spklr rough in 6/21/2001 9:36:33 AM
|
FIRE-Final Inspection | 6/19/2001 | 6/20/2001 | 6/20/2001 | A | PART |
Joe Tawney
|
|
|
Spklr rough in Add two hangers per C/N All else OK
6/20/2001 12:00:19 PM
|
FIRE-Final Inspection | 6/18/2001 | 6/19/2001 | 6/19/2001 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/18/2001 at 14:30:05. Contact: ###-####. done by 406 6/19/2001 1:10:33 AM
|
BLD-Framing/Rough-in | 5/17/2001 | 5/18/2001 | 5/18/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 12:03:18. Contact: ###-####.ok to rock architect approved as built front wall. 12/18/2001 2:55:10 PM
|
BLD-Framing/Rough-in | 5/17/2001 | 5/18/2001 | 5/18/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 12:03:18. Contact: ###-####.ok to rock architect approved as built front wall. 12/18/2001 2:55:10 PM
|
BLD-Framing/Rough-in | 5/14/2001 | 5/15/2001 | 5/15/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/14/2001 at 20:25:38. Contact: ###-####. store front not per plans need resubmital, ok to cover rear area after ele approval c/n posted. 12/15/2001 12:14:24 PM
|