Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD01-00416
StatusFinaled
Name EXECUTRAIN OF BOISE
Site Address 8950 W EMERALD Unit: 178
Project NameCASCADE PLAZA - STE 178
Customer Number 
ePlanReviewNo
Description
(EXECUTRAIN OF BOISE - CASCADE PLAZA - STE 178) New 5,141 sq. ft. tenant space for computer training and office use in shell building (BLD98-02115) per approved plans on file. Work to include new accessible restrooms, new exterior door for second exit, new interior walls with doors, interior finish, new suspended ceiling, fire sprinkler work, plumbing work, mechanical work including installation of (3) additional HVAC rooftop units, and electrical work. One-hour rated tenant demising walls are existing from adjacent tenant improvement projects. NOTE: This building is fully fire sprinklered for area increase. (PC#0146-01) JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/8/20016/11/20016/11/2001APASS
DetailsTom Arcoraci
fn occ-- call 1st before-insp ---- bob ###-#### ok for perm occ 6/10/2001 8:27:26 PM
Permanent Occupancy 6/11/20016/11/2001 DONE
Details
BLD-Final5/14/20015/14/20015/14/2001PPART
DetailsRuss Owen
bob ###-#### ok temp oc needs safety glass at new door,lower toilet paper 1-1/2 under grab rails rest rooms. 12/14/2001 3:38:44 PM
FIRE-Final Inspection5/14/20015/14/20015/14/2001PPASS
DetailsJoe Tawney
Reinsp OK for permanant occupancy 5/14/2001 1:18:25 PM
BLD-Final5/10/20015/11/20015/11/2001PNR
DetailsRuss Owen
###-#### needs fire /life safety before calling for final. 12/11/2001 1:04:11 PM
FIRE-Final Inspection5/10/20015/11/20015/11/2001AFAIL
DetailsJoe Tawney
bob ###-#### Final Fail Several duct det improperly installed 5/11/2001 11:24:17 AM
FIRE-Final Inspection5/7/20015/8/20015/8/2001PNR
DetailsJoe Tawney
bob ###-#### Not ready . Work not completed. 5/8/2001 2:59:30 PM
BLD-Other5/1/20015/2/20015/2/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 05/01/2001 at 08:24:47. Contact: ###-####. ceiling grid. req 1 pod in left side needed. 12/2/2001 10:38:54 AM
FIRE-Final Inspection5/1/20015/2/20015/2/2001APART
DetailsJoe Tawney
###-#### OK on spklr rough in 5/2/2001 10:29:13 AM
BLD-Framing/Rough-in4/9/20014/10/20014/10/2001ACANC
DetailsJim Sly
Scheduled by a contractor via Hello! on 04/09/2001 at 16:44:58. Contact: ###-####. Contr called in wrong job. 4/10/2001 10:49:22 AM
BLD-Framing/Rough-in3/29/20013/30/20013/30/2001PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 03/29/2001 at 14:54:46. Contact: ###-####.ok to sheetrock 3/30/2001 4:50:13 PM