BLD-Final | 5/4/2001 | 5/4/2001 | 5/4/2001 | P | CANC |
Russ Owen
|
|
|
justin- ###-#### fn occ done by 420 at am. 12/4/2001 12:53:42 PM
|
BLD-Final | 5/4/2001 | 5/4/2001 | 5/4/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 5/4/2001 9:11:25 AM C. of C. #21442 issued. 5/4/2001 11:06:33 AM
|
BLD-Energy code compliance | 4/9/2001 | 4/9/2001 | 4/9/2001 | P | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 4/9/2001 2:52:39 PM
|
BLD-Framing/Rough-in | 4/9/2001 | 4/9/2001 | 4/9/2001 | P | PASS |
Jim Storey
|
|
|
###-#### c/n made ok 4/9/2001 2:52:22 PM
|
BLD-Framing/Rough-in | 4/4/2001 | 4/4/2001 | 4/4/2001 | P | FAIL |
Jim Storey
|
|
|
fr insp -justin ###-####
|
BLD-Framing/Rough-in | 4/4/2001 | 4/4/2001 | 4/4/2001 | A | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/4/2001 10:47:31 AM Add straps, clips at rim. Show eng'g for bldg & trusses; complete fireblocks at soffit. ok to insul only
|
BLD-Framing/Rough-in | 4/3/2001 | 4/3/2001 | 4/3/2001 | P | FAIL |
Jim Storey
|
|
|
###-#### no mec approval no insp. 4/3/2001 4:39:22 PM
|
BLD-Framing/Rough-in | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | PASS |
Jim Storey
|
|
|
shear nail Justin ###-####
|
BLD-Framing/Rough-in | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | FAIL |
Steven Webb
|
|
|
SHEAR NAIL JUSTIN ###-#### C/N posted-additional nailing needed to achieve 4" & 12", completion of hd's 3/19/2001 1:20:56 PM
|
BLD-Foundation | 3/7/2001 | 3/7/2001 | 3/7/2001 | P | PART |
Steven Webb
|
|
|
###-#### hd not installed at time of inspection. 3/7/2001 1:27:21 PM
|
BLD-Footing | 3/1/2001 | 3/1/2001 | 3/1/2001 | P | PART |
Dave Hannah
|
|
|
###-#### already poured 3/1/2001 4:05:03 PM
|