FIRE-Final Inspection | 4/15/2002 | 4/16/2002 | 4/16/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life safety and fire sprinkler OK 4/16/2002 12:39:40 PM
|
Permanent Occupancy | | 4/16/2002 | 4/16/2002 | | DONE |
|
|
|
|
BLD-Final | 4/8/2002 | 4/10/2002 | 4/10/2002 | P | PART |
Tom Arcoraci
|
|
|
dennis- ###-#### -re-insp ok for perm occ pending fire sign off needs added sprinkler ect 4/10/2002 3:29:28 PM
|
FIRE-Final Inspection | 4/8/2002 | 4/10/2002 | 4/10/2002 | P | NR |
Troy Cobbley
|
|
|
sprinkler contractor had not finished work at time of AM inspection. I returned at 4:15 and no one was at site and doors were locked 4/10/2002 4:36:30 PM
|
BLD-Final | 4/3/2002 | 4/5/2002 | 4/5/2002 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/03/2002 at 14:19:00. Contact: ###-####.
|
BLD-Final | 4/4/2002 | 4/5/2002 | 4/5/2002 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 4/4/2002 10:01:14 AM
|
BLD-Final | 4/5/2002 | 4/5/2002 | 4/5/2002 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 07:50:44. Contact: ###-####. cn posted 4/5/2002 3:59:05 PM
|
FIRE-Final Inspection | 4/5/2002 | 4/5/2002 | 4/5/2002 | P | FAIL |
Troy Cobbley
|
|
|
add sprinkler head in south east corner of space, provide current inspection tag for fire sprinkler system 4/5/2002 12:44:28 PM
|
Code Occupancy Approval | | | 4/5/2002 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/7/2002 | 1/7/2002 | 1/7/2002 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 11/1/2001 | 11/7/2001 | 11/7/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 11/1/2001 9:31:27 AM meet at 10 am meet for plan re submittal 11/7/2001 10:37:21 AM
|