Permit Information
Permit NumberBLD01-00534
StatusFinaled
Name HANOVER COMPANY
Site Address 490 N MORNINGSIDE WAY
Project NameHILLSIDE
Customer Number 
ePlanReviewNo
Description
To construct a 3057 sq. ft. two story single family dwelling with a 2682 sq. ft. basement (1881 sq. ft. finished)(801 sq. ft. unfinished), a 1126 sq. ft. attached four car garage, 822 sq. ft. of covered concrete patio areas, 417 sq. ft. of covered deck systems off main level and a 69 sq. ft. covered deck off 2nd level per approved plans, all engineering/red-lining and attached requirement lists. Seperate permits will be required to convert any unfinished basement area into habital space. (1st floor 2658 sq. ft.)(2nd floor 801 sq. ft.) This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof system and defensible area is required. Structure will require the installation of a NFPA 13D fire sprinkler system as requlated by the Fire Department. Sprinkler flow alarm shall be attached to the residence smoke detection sytem. PC #195 DJO 12/14/2001 "801s.f. of this basement jas been finished. minimum value allowed for this finish is $15.50 per s.f. for a total value of $12,415 added value to this permit. pep 12/14/2001"
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Grading Inspection7/22/20027/25/20027/25/2002PDONE
DetailsRita DeYoung
Scheduled by a contractor via Hello! on 07/22/2002 at 14:52:43. Contact: ###-####.ok via ph per T. R. 7/25/2002 3:28:49 PM
BLD-Final12/17/200112/17/200112/17/2001PPASS
DetailsTony Young
Scheduled by a contractor via Hello! on 12/17/2001 at 09:34:32. Contact: ###-####.c of c issued 12/17/2001 2:02:18 PM
BLD-Final12/13/200112/14/200112/14/2001AFAIL
DetailsTony Young
c/n posted on erics notebook, more of a conf. 12/14/2001 1:24:08 PM
FIRE-Final Inspection12/13/200112/14/200112/14/2001APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/13/2001 at 17:07:23. Contact: ###-####.
BLD-Final12/12/200112/13/200112/13/2001ANR
DetailsTony Young
Scheduled by a contractor via Hello! on 12/12/2001 at 12:47:20. Contact: ###-####.
BLD-Grading Inspection12/13/200112/13/200112/13/2001 BOND
DetailsRita DeYoung
Rough grading is complete. Fine grading and storm drain connection are not complete. For the incomplete items the engineer has recommended a $2250.00 bond. The bond has been submitted.
FIRE-Final Inspection12/12/200112/13/200112/13/2001ANR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/12/2001 at 16:08:23. Contact: ###-####.
BLD-Final12/12/200112/12/200112/12/2001PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 12/12/2001 at 10:40:53. Contact: ###-####.conf. only,,,not ready 12/12/2001 3:55:40 PM
FIRE-Conference11/26/200111/26/200111/26/2001PPART
DetailsRick Jackson
Added by Inspector: 409 On 11/26/2001 2:04:02 PM alarm requirements for sprinklers
BLD-Conference10/22/200110/22/200110/22/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 10/22/2001 8:47:20 AM w/ bldr...keep c/n
BLD-Conference10/4/200110/4/200110/4/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 10/4/2001 6:05:15 PM keep c/n
BLD-Framing/Rough-in9/11/20019/11/20019/11/2001PPART
DetailsTony Young
ok to cover after gas test passes and all 3 fireplaces have permits 9/11/2001 1:06:40 PM
BLD-Wall cover9/10/20019/11/20019/11/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 09/10/2001 at 10:14:08. Contact: ###-####.
FIRE-Final Inspection9/10/20019/10/20019/10/2001PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/10/2001 at 10:18:23. Contact: ###-####.
FIRE-Sprinkler Rough-in9/10/20019/10/20019/10/2001PPART
DetailsRick Jackson
Added by Inspector: 409 On 9/10/2001 2:04:07 PM okay to cover
BLD-Framing/Rough-in9/6/20019/7/20019/7/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 09/06/2001 at 11:31:20. Contact: ###-####.
c/n posted, ok to insulate pending trade inspector approval 9/7/2001 12:09:26 PM
FIRE-Sprinkler Rough-in9/6/20019/6/20019/6/2001AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 9/6/2001 9:45:01 AM need tenting completed prior to covering ceilings
BLD-Wall cover9/4/20019/5/20019/5/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 09/04/2001 at 17:41:53. Contact: ###-####.ext. shear ok w/ nailing at marked areas, verify hold downs on interior at framing inspection 9/5/2001 11:54:44 AM
BLD-Wall cover9/4/20019/4/20019/4/2001PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 09/04/2001 at 08:21:20. Contact: ###-####.
c/n posted on shear nailing 9/4/2001 1:29:06 PM
BLD-Wall cover8/24/20018/27/20018/27/2001AFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 08/24/2001 at 15:40:31. Contact: ###-####.
c/n posted, old c/n removed by me 8/27/2001 12:33:21 PM
BLD-Framing/Rough-in8/10/20018/15/20018/15/2001PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 08/10/2001 at 19:43:07. Contact: ###-####.
prior c/n still governs 8/15/2001 2:17:40 PM
BLD-Framing/Rough-in8/13/20018/13/20018/13/2001PFAIL
DetailsTony Young
hold downs and shear
c/n posted on hold downs and nailing 8/13/2001 2:48:10 PM
BLD-Framing/Rough-in8/10/20018/13/20018/13/2001ANR
DetailsTony Young
shear and hold downs 8/13/2001 8:13:51 AM
BLD-Wall cover8/10/20018/13/20018/13/2001PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 08/10/2001 at 19:42:04. Contact: ###-####.same as before, c/n posted 8/13/2001 2:48:44 PM
BLD-Framing/Rough-in8/10/20018/10/20018/10/2001PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 08/10/2001 at 08:21:42. Contact: ###-####.
not ready, hold downs not in yet 8/10/2001 2:05:23 PM
BLD-Aging Inspection7/16/20017/16/20017/16/2001 CANC
DetailsTony Young
wip?? 7/16/2001 9:04:15 AM
BLD-Footing5/15/20015/15/20015/15/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 05/15/2001 at 10:35:38. Contact: ###-####.
BLD-Foundation5/15/20015/15/20015/15/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 05/15/2001 at 10:36:19. Contact: ###-####.
wip, ok after verbal corrections 5/15/2001 12:36:20 PM
BLD-Grading Inspection5/3/20015/3/20015/3/2001 PASS
DetailsRita DeYoung
Footing subgrade has been approved by the engineer
BLD-Footing4/27/20014/30/20014/30/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 04/27/2001 at 13:49:18. Contact: ###-####.
work in progress, verbal corrections, waiting on letter from eng. on sub grade, ok to pour after 4/30/2001 12:24:17 PM