BLD-Final | 4/3/2002 | 4/4/2002 | 4/4/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/03/2002 at 15:16:51. Contact: ###-####. ok for c/o 4/4/2002 11:57:16 AM
|
Permanent Occupancy | | 4/4/2002 | 4/4/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/26/2002 | 3/26/2002 | 3/26/2002 | P | PASS |
Rick Jackson
|
|
|
###-####
|
FIRE-Final Inspection | 2/28/2002 | 3/1/2002 | 3/1/2002 | A | FAIL |
Rick Jackson
|
|
|
frank ###-#### fire fn need address and heat in sprinkler riser room 3/1/2002 11:45:32 AM
|
FIRE-Final Inspection | 2/20/2002 | 2/25/2002 | 2/25/2002 | A | FAIL |
Rick Jackson
|
|
|
###-#### 9am need building address; need fire alarma nd sprinkler completed and pass 2/25/2002 11:02:23 AM
|
BLD-Energy code compliance | 11/26/2001 | 11/27/2001 | 11/27/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/26/2001 at 10:43:08. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/21/2001 | 11/23/2001 | 11/23/2001 | A | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Conference | 10/23/2001 | 10/24/2001 | 10/24/2001 | A | PASS |
Jim Storey
|
|
|
###-#### fire blk/ fire stopping and shaft. 10/24/2001 3:44:31 PM
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | PASS |
Jim Storey
|
|
|
wip 10/8/2001 4:48:00 PM
|
BLD-Concrete | 8/6/2001 | 8/7/2001 | 8/7/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/06/2001 at 08:44:32. Contact: ###-####.s-i on site. 8/7/2001 12:07:19 PM
|
BLD-Foundation | 7/24/2001 | 7/25/2001 | 7/25/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/24/2001 at 15:00:22. Contact: ###-####. placed with special insp. pending report. 7/25/2001 10:17:56 AM
|
BLD-Footing | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/20/2001 at 09:21:44. Contact: ###-####.
special inspector on site, ok pending report,, not set up all the way 6/21/2001 11:07:06 AM
|