BLD-Final | 6/7/2002 | 6/10/2002 | 6/10/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/07/2002 at 14:13:08. Contact: ###-####. final ok 6/10/2002 9:59:47 AM
|
Permanent Occupancy | | 6/10/2002 | 6/10/2002 | | DONE |
|
|
|
|
Code Occupancy Approval | 6/7/2002 | 6/7/2002 | 6/7/2002 | P | PASS |
Wm. Michael Meloy
|
|
|
|
FIRE-Final Inspection | 5/15/2002 | 5/15/2002 | 5/16/2002 | P | FAIL |
Rick Jackson
|
|
|
BUILING #27 ###-#### alarms not working properly; not sending signals to main panel 5/16/2002 3:14:28 PM
|
BLD-Energy code compliance | 2/21/2002 | 2/21/2002 | 2/21/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/21/2002 at 08:55:21. Contact: ###-####. framing ok and insulation ok for cover, 2/21/2002 5:01:56 PM
|
BLD-Framing/Rough-in | 2/15/2002 | 2/19/2002 | 2/19/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/15/2002 at 15:41:20. Contact: ###-####. ok to insulate/ 2 and 3rd fl gyp protection. 2/19/2002 3:59:29 PM
|
BLD-Aging Inspection | 10/29/2001 | 10/29/2001 | 10/29/2001 | | PASS |
Jim Storey
|
|
|
wip 11/5/2001 7:11:05 AM
|
BLD-Concrete | 8/27/2001 | 8/28/2001 | 8/28/2001 | A | DONE |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/27/2001 at 08:02:14. Contact: ###-####. already poured--special inspection 8/28/2001 11:15:59 AM
|
BLD-Foundation | 8/7/2001 | 8/8/2001 | 8/8/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/07/2001 at 14:20:39. Contact: ###-####. ok pend report 8/8/2001 8:33:03 AM
|
BLD-Footing | 7/24/2001 | 7/25/2001 | 7/25/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/24/2001 at 15:02:30. Contact: ###-####. placed with special insp. pending report. 7/25/2001 10:17:32 AM
|