BLD-Final | 2/11/2002 | 2/12/2002 | 2/12/2002 | P | DONE |
Tom Arcoraci
|
|
|
###-####
|
BLD-Final | 2/12/2002 | 2/12/2002 | 2/12/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 2/12/2002 9:47:21 AM ok for perm occ 2/12/2002 9:56:09 AM
|
Permanent Occupancy | | 2/12/2002 | 2/12/2002 | | DONE |
|
|
|
|
BLD-Final | 1/15/2002 | 1/17/2002 | 1/17/2002 | P | PART |
Tom Arcoraci
|
|
|
###-#### ok for temp occ needs to complete items for perm occ on shell and core permit see notes on that permit 1/17/2002 2:20:57 PM 1/17/2002 2:21:32 PM 1/17/2002 2:27:54 PM
|
BLD-Final | 1/15/2002 | 1/17/2002 | 1/17/2002 | A | NR |
Tom Arcoraci
|
|
|
###-####
|
FIRE-Final Inspection | 1/17/2002 | 1/17/2002 | 1/17/2002 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 1/17/2002 2:04:32 PM Fire life/safety, fire alarm and fire sprinkler system finaled
|
FIRE-Final Inspection | 1/15/2002 | 1/17/2002 | 1/17/2002 | A | CANC |
Troy Cobbley
|
|
|
canceled by contractor 1/17/2002 9:14:55 AM
|
BLD-Other | 12/10/2001 | 12/10/2001 | 12/10/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/10/2001 at 08:22:01. Contact: ###-####. grid ok 12/10/2001 1:10:59 PM
|
BLD-Wall cover | 11/29/2001 | 11/30/2001 | 11/30/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 11/29/2001 9:12:47 AM grid inspection grid ok 11/30/2001 10:30:43 AM
|
BLD-Other | 11/27/2001 | 11/29/2001 | 11/29/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/27/2001 at 15:19:41. Contact: ###-####. fix wires not installed 11/29/2001 10:31:40 AM
|
BLD-Conference | 11/21/2001 | 11/26/2001 | 11/26/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/21/2001 at 11:47:44. Contact: ###-####. 350 sq ft sesmic pods ok 11/26/2001 10:33:05 AM
|
BLD-Aging Inspection | 10/2/2001 | 10/2/2001 | 10/2/2001 | | PART |
Tom Arcoraci
|
|
|
wip 10/2/2001 2:15:50 PM
|