BLD-Final | 8/23/2001 | 8/24/2001 | 8/24/2001 | A | PASS |
Carl Dependahl
|
|
|
DOC- ###-####-PLEASE CALL 1/2 BEFORE INSP -FN final ok for l/c only. rec'd MTI insp report ok. 8/24/2001 11:25:11 AM
|
FIRE-Final Inspection | 8/23/2001 | 8/23/2001 | 8/23/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/23/2001 9:54:35 AM
|
FIRE-Final Inspection | 8/21/2001 | 8/22/2001 | 8/22/2001 | A | NR |
Rick Jackson
|
|
|
###-#### will reschedule for 8/23/01 8/22/2001 11:47:14 AM
|
BLD-Foundation | 7/25/2001 | 7/26/2001 | 7/26/2001 | A | PASS |
Jim Storey
|
|
|
masonry John ###-#### ok for grout. 7/26/2001 7:46:10 AM
|
BLD-Foundation | 7/25/2001 | 7/25/2001 | 7/25/2001 | P | PASS |
Jim Storey
|
|
|
re-bar John ###-#### verts ok reviewed 30 inch requirment ok. 7/25/2001 2:53:58 PM
|
BLD-Framing/Rough-in | 7/13/2001 | 7/13/2001 | 7/13/2001 | P | PART |
Carl Dependahl
|
|
|
fire wall insp- ###-#### --doc ; ok to complete gyp at 4hr wall infills 7/13/2001 4:32:59 PM
|
BLD-Framing/Rough-in | 7/11/2001 | 7/11/2001 | 7/11/2001 | P | PART |
Carl Dependahl
|
|
|
###-####; ok to begin wall infill, cover at stairs. 7/11/2001 5:11:31 PM
|
BLD-Framing/Rough-in | 6/29/2001 | 7/2/2001 | 7/2/2001 | A | PART |
Russ Owen
|
|
|
call first ###-####.need changes to stirway construction on new plan also the 4 hour infill to existing wall has not been constructed. c/n posted on job card,ok to rock 1 side. 7/2/2001 11:24:46 AM
|
BLD-Footing | 6/7/2001 | 6/8/2001 | 6/8/2001 | A | PASS |
Jim Storey
|
|
|
doc please give one hour notice if you can please ###-####interior footing
|