BLD-Final | 8/21/2001 | 8/22/2001 | 8/22/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/21/2001 at 11:40:21. Contact: ###-####. l/c only final ok 8/23/2001 3:47:53 PM
|
BLD-Conference | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/21/2001 3:01:34 PM w/ jason re final
|
BLD-Final | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/17/2001 at 11:35:13. Contact: ###-####...need elec ok 8/20/2001 10:21:50 AM
|
FIRE-Final Inspection | 8/7/2001 | 8/8/2001 | 8/8/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/07/2001 at 07:34:09. Contact: ###-####.
|
FIRE-Final Inspection | 8/3/2001 | 8/6/2001 | 8/6/2001 | A | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/03/2001 at 07:52:10. Contact: ###-####.
|
FIRE-Final Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/06/2001 at 07:58:50. Contact: ###-####.
|
FIRE-Final Inspection | 8/1/2001 | 8/2/2001 | 8/2/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/01/2001 at 16:33:00. Contact: ###-####. alarms not ready 8/3/2001 9:02:04 AM
|
BLD-Framing/Rough-in | 6/25/2001 | 6/26/2001 | 6/26/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/25/2001 at 11:20:01. Contact: ...complete firestops & damper install; ok to continue 6/26/2001 11:18:02 AM
|