To construct a 2234 sq. ft. single story DUPLEX. Each unit is a three bedroom, two bath 1117 sq. ft. with a 459 sq. ft. two car garage. Per approved plans and requirement list. NOTE: THIS UNIT IS BEING CONSTRUCTED AS A DUPLEX AND CANNOT BE CONVERTED OR SOLD AS INDIVIDUAL UNITS OR TOWNHOUSES. PC#318 (SAM)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/29/20028/30/20028/30/2002APASS
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung c.c # 17627 issued 8/30/2002 10:34:47 AM
BLD-Final8/28/20028/29/20028/29/2002ACANC
DetailsDave Hannah
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Final8/29/20028/29/20028/29/2002PCANC
DetailsDave Hannah
BLD-Conference8/7/20028/7/20028/7/2002PDONE
DetailsDave Hannah
needs extension please ###-#### mike work in progress ext 90 days 8/7/2002 2:40:52 PM
BLD-Energy code compliance1/30/20021/31/20021/31/2002APASS
DetailsDave Hannah
###-#### ok to cover 1/31/2002 9:35:30 AM
BLD-Energy code compliance1/30/20021/31/20021/31/2002APASS
DetailsDave Hannah
###-####
BLD-Framing/Rough-in1/23/20021/24/20021/24/2002APASS
DetailsDave Hannah
###-#### ok to insulate 1/24/2002 12:44:42 PM
BLD-Framing/Rough-in1/16/20021/17/20021/17/2002AFAIL
DetailsDave Hannah
Scheduled by Inspector: 425 On 1/16/2002 4:21:08 PM c/n on site 1/17/2002 11:04:06 AM
BLD-Framing/Rough-in1/16/20021/16/20021/16/2002PCANC
DetailsDave Hannah
###-####
BLD-Framing/Rough-in12/13/200112/14/200112/14/2001APART
DetailsDave Hannah
###-#### TWO one hour walls between garages pass ok to close up 12/14/2001 10:51:54 AM
BLD-Framing/Rough-in12/7/200112/10/200112/10/2001APART
DetailsDave Hannah
###-#### MIKE FOR 9310 ONLY shear ok to cover ext 12/10/2001 10:03:49 AM
BLD-Other12/10/200112/10/200112/10/2001PCANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/10/2001 at 07:34:06. Contact: .
BLD-Aging Inspection11/12/200111/12/200111/12/2001 DONE
DetailsDave Hannah
work in progress 11/13/2001 9:10:44 AM
BLD-Aging Inspection9/10/20019/10/20019/10/2001 DONE
DetailsDave Hannah
exp on 1/9/02 9/10/2001 10:03:17 AM
BLD-Footing7/6/20017/9/20017/9/2001PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 07/06/2001 at 09:41:03. Contact: ###-####. work in progress 7/9/2001 3:33:19 PM