Permit Information
Permit NumberBLD01-01377
StatusFinaled
Name BOISE CASCADE CORPORATION
Site Address 1111 W JEFFERSON ST
Project NameBOISE CASCADE
Customer Number 
ePlanReviewNo
Description
(BOISE CASCADE-BASEMENT) Phase I of an agreement on file to upgrade exiting system in basement of existing building. Work to include providing a one-hour rated elevator lobby, some one-hour rated wall portions in existing rated corridor, providing 20 minute rated doors and 45 minute rated wire glass in rated elevator lobby walls and rated corridor wall, smoke/fire damper installations at wall penetrations, suspended ceiling adjustments, alarm work, mechanical work, and electrical work. This is a Scope of Work Permit. LETTER OF COMPLETION TO BE ISSUED WHEN DONE. NOTE: This building is fully fire sprinklered and alarmed. (P.C.#0433-01) JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/5/200311/6/200311/6/2003APASS
DetailsDave Hannah
###-#### charlie ok for cc 11/6/2003 9:22:53 AM
FIRE-Final Inspection11/5/200311/5/200311/5/2003PPASS
DetailsRick Jackson
###-#### charlie
FIRE-Final Inspection10/23/200310/23/200310/23/2003APASS
DetailsRick Jackson
BLD-Aging Inspection8/27/20038/27/20038/27/2003 DONE
DetailsDave Hannah
wip 8/27/2003 9:10:46 AM
BLD-Aging Inspection6/25/20036/25/20036/25/2003 PASS
DetailsCarl Dependahl
wip 6/25/2003 10:07:20 AM
BLD-Aging Inspection4/25/20034/25/20034/28/2003 PASS
DetailsCarl Dependahl
phased project, WIP... 4/28/2003 9:06:20 AM
BLD-Framing/Rough-in2/6/20032/7/20032/7/2003APART
DetailsCarl Dependahl
###-####...more tunnel...wip, doors back ordered2/7/2003 11:23:49 AM 2/7/2003 11:37:54 AM
BLD-Framing/Rough-in2/6/20032/6/20032/6/2003PPART
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung....tunnel corridor w 2/6/2003 3:54:56 PM ip 2/6/2003 3:55:06 PM
BLD-Framing/Rough-in1/22/20031/23/20031/23/2003ACANC
DetailsCarl Dependahl
###-####
BLD-Framing/Rough-in1/23/20031/23/20031/23/2003PPART
DetailsCarl Dependahl
charlie ...arch's detail onsite to "tunnel corridor; seal bulkeads to elev. lobby at bsmt, phase 1 of project. 1/23/2003 3:03:39 PM
BLD-Conference1/14/20031/14/20031/14/2003PFAIL
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung, c/n need detail & clarification re elev lobby/corridor. 1/14/2003 3:46:42 PM
BLD-Conference10/10/200210/10/200210/10/2002PPASS
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Amy Lawson...work slowww 10/10/02 3:02:17 PM