BLD-Final | 11/5/2003 | 11/6/2003 | 11/6/2003 | A | PASS |
Dave Hannah
|
|
|
###-#### charlie ok for cc 11/6/2003 9:22:53 AM
|
FIRE-Final Inspection | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | PASS |
Rick Jackson
|
|
|
###-#### charlie
|
FIRE-Final Inspection | 10/23/2003 | 10/23/2003 | 10/23/2003 | A | PASS |
Rick Jackson
|
|
|
|
BLD-Aging Inspection | 8/27/2003 | 8/27/2003 | 8/27/2003 | | DONE |
Dave Hannah
|
|
|
wip 8/27/2003 9:10:46 AM
|
BLD-Aging Inspection | 6/25/2003 | 6/25/2003 | 6/25/2003 | | PASS |
Carl Dependahl
|
|
|
wip 6/25/2003 10:07:20 AM
|
BLD-Aging Inspection | 4/25/2003 | 4/25/2003 | 4/28/2003 | | PASS |
Carl Dependahl
|
|
|
phased project, WIP... 4/28/2003 9:06:20 AM
|
BLD-Framing/Rough-in | 2/6/2003 | 2/7/2003 | 2/7/2003 | A | PART |
Carl Dependahl
|
|
|
###-####...more tunnel...wip, doors back ordered2/7/2003 11:23:49 AM 2/7/2003 11:37:54 AM
|
BLD-Framing/Rough-in | 2/6/2003 | 2/6/2003 | 2/6/2003 | P | PART |
Carl Dependahl
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung....tunnel corridor w 2/6/2003 3:54:56 PM ip 2/6/2003 3:55:06 PM
|
BLD-Framing/Rough-in | 1/22/2003 | 1/23/2003 | 1/23/2003 | A | CANC |
Carl Dependahl
|
|
|
###-####
|
BLD-Framing/Rough-in | 1/23/2003 | 1/23/2003 | 1/23/2003 | P | PART |
Carl Dependahl
|
|
|
charlie ...arch's detail onsite to "tunnel corridor; seal bulkeads to elev. lobby at bsmt, phase 1 of project. 1/23/2003 3:03:39 PM
|
BLD-Conference | 1/14/2003 | 1/14/2003 | 1/14/2003 | P | FAIL |
Carl Dependahl
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung, c/n need detail & clarification re elev lobby/corridor. 1/14/2003 3:46:42 PM
|
BLD-Conference | 10/10/2002 | 10/10/2002 | 10/10/2002 | P | PASS |
Carl Dependahl
|
|
|
Phone #: ###-#### Internet Inspection Request from: Amy Lawson...work slowww 10/10/02 3:02:17 PM
|