BLD-Final | 11/28/2001 | 11/30/2001 | 11/30/2001 | P | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/28/2001 at 07:34:30. Contact: ###-####. Cancelled by contractor 11/29/2001 8:38:13 AM
|
BLD-Final | 11/28/2001 | 11/28/2001 | 11/28/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/28/2001 at 07:36:15. Contact: ###-####. c. of c. #20947 issued. 11/28/2001 2:16:40 PM
|
BLD-Energy code compliance | 9/24/2001 | 9/24/2001 | 9/24/2001 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 09/24/2001 at 11:03:49. Contact: ###-####. Need energy report prior to issuance of c. of c. 9/24/2001 3:31:54 PM
|
BLD-Framing/Rough-in | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 09/19/2001 at 15:03:04. Contact: ###-####. c/n issued--ok to insulate 9/20/2001 10:10:17 AM
|
BLD-Conference | 8/2/2001 | 8/2/2001 | 8/2/2001 | | PART |
Bob Archibald
|
|
|
contractor can work over stopwork order till aug 9th per Tim H. for inspections call Bob.
|
BLD-Other | 8/1/2001 | 8/1/2001 | 8/1/2001 | P | PART |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 8/1/2001 2:46:41 PM Issued 2nd stop work order due to flood plain issues. B. Archibald directed me to issue this 2nd one, Marlene and Jennifer were consulted to by understanding. Informed Builder to comply with stop work and resolve this situation . 8/1/2001 2:54:30 PM
|
BLD-Other | 7/25/2001 | 7/25/2001 | 7/25/2001 | A | DONE |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 7/25/2001 8:59:07 AM Per Inspector#325 issued Stop
Work Order, Engineer to contact Jim Wylie--Flood Plain Issue. 7/25/2001 9:00:55 AM
|
BLD-Framing/Rough-in | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | PASS |
Steven Webb
|
|
|
###-#### ok to side 7/23/2001 2:15:56 PM
|
BLD-Footing | 6/19/2001 | 6/19/2001 | 6/19/2001 | P | PART |
Steven Webb
|
|
|
###-#### wip 6/19/2001 1:50:35 PM
|