BLD-Final | 11/12/2001 | 11/13/2001 | 11/13/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/12/2001 at 10:31:21. Contact: ###-####. C/C issued. 11/13/2001 9:05:24 AM
|
BLD-Final | 11/9/2001 | 11/12/2001 | 11/12/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/09/2001 at 14:39:07. Contact: ###-####. C/C issued. 11/13/2001 9:31:12 AM
|
BLD-Energy code compliance | 9/6/2001 | 9/11/2001 | 9/11/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 09/06/2001 at 12:43:09. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/6/2001 | 9/7/2001 | 9/7/2001 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/06/2001 at 12:42:14. Contact: ###-####. c/n on site ok to insulate 9/7/2001 2:24:09 PM
|
BLD-Framing/Rough-in | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | PART |
Jim Sly
|
|
|
###-#### mike sheer panel Shear OK. 8/24/2001 5:50:03 PM
|
BLD-Foundation | 8/5/2001 | 8/6/2001 | 8/6/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/05/2001 at 21:17:06. Contact: ###-####.
|
BLD-Foundation | 7/11/2001 | 7/12/2001 | 7/12/2001 | A | PASS |
Dave Hannah
|
|
|
###-####
|
BLD-Footing | 7/10/2001 | 7/11/2001 | 7/11/2001 | A | PASS |
Jim Sly
|
|
|
Mike ###-####
|