Permit Information
Permit NumberBLD01-01850
StatusFinaled
Name GUARANTEED QUALITY HOMES
Site Address 1551 W WARREN ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a five bedroom, three and half bathroom 1424 sq. ft. two story single family dwelling (692 sq. ft. first floor/732 sq. ft. second floor) with a attached 608 sq. ft. finished --(UNFINISHED 10/18/01)-- basement, a 484 sq. ft. DETACHED two car garage and a 90 sq. ft. covered front porch. Per approved plans and requirement list. PC#558 (SAM) 10/18/01 BASEMENT TO BE UNFINISHED. A SEPARATE PERMIT IS REQUIRED TO FINISHED BASEMENT. ONLY MINIMUM ELECTRICAL, MECHANICAL, PLUMBING TO BE INSTALLED IN BASEMENT. (SAM)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/17/200112/18/200112/18/2001APASS
DetailsJim Storey
call first ###-#### final ok 12/18/2001 5:19:58 PM
BLD-Final12/14/200112/17/200112/17/2001AFAIL
DetailsJim Storey
TRAVIS ###-#### c/n posted 12/17/2001 10:48:28 AM
BLD-Final12/13/200112/14/200112/14/2001AFAIL
DetailsDave Hannah
###-#### needs mec c/n corrected and finaled and struc c/n correceted 12/14/2001 9:57:40 AM
BLD-Final12/12/200112/13/200112/13/2001PNR
DetailsRuss Owen
TRAVIS ###-####
BLD-Energy code compliance11/2/200111/5/200111/5/2001APASS
DetailsSteven Webb
travis ###-#### 11/5/2001 9:04:55 AM
BLD-Framing/Rough-in11/2/200111/5/200111/5/2001APART
DetailsSteven Webb
fr insp travis- ###-#### c/n issued--ok to cover except projection to low in stairwell leading to the basement--code requires finish min. of 6'8".Marked with yellow craoyon, do not cover on projection--correct and call for re-inspection. 11/5/2001 9:06:40 AM
BLD-Energy code compliance10/31/200111/1/200111/1/2001AFAIL
DetailsSteven Webb
###-#### prior c/n items not completed--re-inspection fee required to be paid prior to next inspection. DO NOT COVER. 11/1/2001 9:18:59 AM
BLD-Framing/Rough-in10/29/200110/30/200110/30/2001PPART
DetailsDave Hannah
###-#### travis seal package is installed but still has several items to complete on org c/n ok to insulate 10/30/2001 1:39:41 PM
BLD-Framing/Rough-in10/26/200110/29/200110/29/2001AFAIL
DetailsSteven Webb
###-#### TRAVIS c/n issued--do not insulate 10/29/2001 9:15:11 AM
BLD-Framing/Rough-in10/17/200110/18/200110/18/2001APART
DetailsTom Arcoraci
###-#### ok to side 10/18/2001 11:06:20 AM
BLD-Framing/Rough-in10/16/200110/16/200110/16/2001PFAIL
DetailsJim Storey
shear travis- ###-#### missing nailling/ 2nd floor weat wall south end strap pannel to 1 st floor. 10/17/2001 11:54:39 AM
BLD-Footing10/4/200110/4/200110/4/2001PPART
DetailsDave Hannah
ft insp- ###-####- travis work in progress 10/4/2001 4:28:58 PM
BLD-Foundation9/17/20019/17/20019/17/2001PPASS
DetailsJim Storey
###-#### JED rebar in walls ok. 9/17/2001 4:58:47 PM
BLD-Footing8/15/20018/15/20018/15/2001PPASS
DetailsJim Storey
jed- ###-####