BLD-Grading Inspection | 9/16/2003 | 9/16/2003 | 9/16/2003 | | BND |
Rita DeYoung
|
|
|
Final grading has been completed. However, the driveway must be completed and a series of retaining walls in the front yard rebuilt to be in compliance with the zoning ordinance. the applicant has submitted a $10,000.00 bond to ensure completion of the driveway and rebuilding of the walls. Therefore the final grading and drainage is conditionally approved.
|
BLD-Final | 9/11/2003 | 9/12/2003 | 9/12/2003 | P | PART |
Jim Storey
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Annette Moore final ok pending terry records sign off for hillside and bond release for driveway. 9/12/2003 3:59:25 PM
|
BLD-Final | 9/10/2003 | 9/11/2003 | 9/11/2003 | P | NR |
Russ Owen
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Barbara Moore I talked with Steve this has not been approved by Terry Records for final grading bond etc, and as per policy , this is to be done prior to inspection. Informed him to recall. 9/10/2003 11:25:07 PM 9/10/2003 11:25:31 PM
|
BLD-Energy code compliance | 4/24/2003 | 4/25/2003 | 4/25/2003 | A | CANC |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 4/25/2003 | 4/25/2003 | 4/25/2003 | P | PASS |
Dave Hannah
|
|
|
ok to cover 4/25/2003 3:37:51 PM
|
BLD-Energy code compliance | 4/23/2003 | 4/24/2003 | 4/24/2003 | A | NR |
Dave Hannah
|
|
|
###-####
|
BLD-Energy code compliance | 4/24/2003 | 4/24/2003 | 4/24/2003 | P | NR |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 3/10/2003 | 3/11/2003 | 3/11/2003 | A | PASS |
Dave Hannah
|
|
|
steven; Phone #: ###-#### Internet Inspection Request from: Darla Downs all c/n items completed also had letter from engineer on point load ok per letter 3/11/2003 11:26:11 AM
|
BLD-Framing/Rough-in | 3/3/2003 | 3/4/2003 | 3/4/2003 | P | FAIL |
Dave Hannah
|
|
|
steven; Phone #: ###-#### Internet Inspection Request from: Darla Downs add this to yesterdays c/n contractor is getting engeering on point load that comes from roof down on to second floor but this section of floor is cantalevered north wall of living room 3/4/2003 4:57:58 PM
|
BLD-Energy code compliance | 3/3/2003 | 3/3/2003 | 3/3/2003 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/3/2003 at 7:37:52 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/3/2003 | 3/3/2003 | 3/3/2003 | P | FAIL |
Dave Hannah
|
|
|
ok to insulate c/n on site
|
BLD-Framing/Rough-in | 1/27/2003 | 1/28/2003 | 1/28/2003 | A | PART |
Dave Hannah
|
|
|
###-#### shear had new approved plans and engineering i review both house is now ok to cover ext 1/28/2003 10:59:13 AM
|
BLD-Framing/Rough-in | 1/2/2003 | 1/3/2003 | 1/3/2003 | A | NR |
Steven Webb
|
|
|
early am ###-####--More conference than framing (shear) most of house covered already--Walked house with owner-No approved plans--Instructed owner to re-submit plans with attached engineering to city for approval-nailing not per plans plus missing hd's --RV garage including rear of house. 1/3/2003 8:58:47 AM
|
BLD-Conference | 9/3/2002 | 9/3/2002 | 9/3/2002 | P | PASS |
Carl Dependahl
|
|
|
w/ Steve Jones...need permits in his name, approved plans, etc...needs to obtain all "trade" ok's for frame insp & verify shear panel nailing (or equal) 9/3/2002 4:00:28 PM
referred to tony & alan H. for more info 9/3/2002 4:01:26 PM
|
BLD-Conference | 7/29/2002 | 7/30/2002 | 7/30/2002 | P | PART |
Tony Young
|
|
|
mike ###-#### please call 1/2 hour before going out so mike can meet you there
conf. what all has happened so-far,,, new cont. 7/30/2002 2:16:01 PM
|
BLD-Conference | 7/16/2002 | 7/16/2002 | 7/16/2002 | P | FAIL |
Tony Young
|
|
|
SWO issued on mechanical, DOUBLE IMPOSED IF NOT OBTAINED BY 5 PM ON 7/17/02
|
BLD-Framing/Rough-in | 7/15/2002 | 7/16/2002 | 7/16/2002 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/15/2002 at 17:08:37. Contact: ###-####.SWO issued on mechanical,, c/n posted to that effect 7/16/2002 12:23:55 PM
|
BLD-Conference | 7/9/2002 | 7/10/2002 | 7/10/2002 | A | PART |
Tony Young
|
|
|
###-#### steve
frame issues, c/n still posted,,, need struct. eng. to give ok on shear 7/10/2002 3:09:50 PM
|
BLD-Conference | 7/10/2002 | 7/10/2002 | 7/10/2002 | P | PART |
Tony Young
|
|
|
mech. walk through 7/10/2002 3:07:27 PM
|
BLD-Conference | 7/8/2002 | 7/9/2002 | 7/9/2002 | A | FAIL |
Carl Dependahl
|
|
|
STEVE ###-#### Need shear insp, plans, etc..wants hvac "consult" but no MEC permit...advised for 415 to resolve as he posted c/n. 7/9/2002 9:21:15 AM
|
BLD-Framing/Rough-in | 5/15/2002 | 5/16/2002 | 5/16/2002 | A | FAIL |
Tony Young
|
|
|
mike ###-####
c/n posted 5/16/2002 12:24:16 PM
|
BLD-Foundation | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PART |
Tony Young
|
|
|
###-#### ERIC
|
BLD-Footing | 12/12/2001 | 12/13/2001 | 12/13/2001 | A | PART |
Tony Young
|
|
|
941--2454 re inspect ftg
recvd. new eng. ok, wip 12/13/2001 2:10:08 PM
|
BLD-Footing | 12/11/2001 | 12/12/2001 | 12/12/2001 | A | PART |
Tony Young
|
|
|
941---2454 footing
forms in place, no rebar 12/12/2001 2:33:50 PM
|
BLD-Footing | 12/11/2001 | 12/11/2001 | 12/11/2001 | P | NR |
Tony Young
|
|
|
###-####
|
BLD-Foundation | 10/29/2001 | 10/30/2001 | 10/30/2001 | A | PART |
Tony Young
|
|
|
###-####
wip 10/30/2001 11:26:11 AM
|
BLD-Foundation | 10/22/2001 | 10/23/2001 | 10/23/2001 | A | PART |
Steven Webb
|
|
|
###-#### MIKE wip--appears ok 10/23/2001 10:42:28 AM
|
BLD-Foundation | 10/15/2001 | 10/15/2001 | 10/15/2001 | P | PART |
Tony Young
|
|
|
###-#### wip 10/15/2001 2:28:21 PM
|
BLD-Grading Inspection | 10/11/2001 | 10/11/2001 | 10/11/2001 | | PASS |
Rita DeYoung
|
|
|
Footing subgrade for basement walls has been approved by the geotechnical engineer
|