Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-01879
StatusFinaled
Name LARRY YOUNG
Site Address 2194 E ROANOKE DR
Project NameHILLSIDE
Customer Number 
ePlanReviewNo
Description
To construct a 1906 sq. ft. two story single family dwelling with a 1050 sq. ft. unfinished basement, a 552 sq. ft. attached two car garage with attic storage and a 300 sq. ft. wood deck off rear of structure per approved plans, all engineering/red-lining and attached requirement lists. (1st floor 1078 sq. ft.)(2nd floor 828 sq. ft.) Seperate permits will be required to finish basement. This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof system and defensible area will be maintained. PC #614 CFH #01-00021 DJO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/7/20046/10/20046/10/2004APASS
DetailsDave Hannah
Larry; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Conference3/2/20043/2/20043/2/2004PPASS
DetailsDave Hannah
justan; Phone #: ###-#### Internet Inspection Request from: Darla Downs
Extend Permit 180 days 3/2/20043/2/2004 PASS
DetailsDave Hannah
Extend Permit 180 days 3/2/20043/2/2004 PASS
DetailsDave Hannah
ok to extend permit
BLD-Conference2/26/20042/26/20042/26/2004ADONE
DetailsDave Hannah
BLD-Final2/23/20042/24/20042/24/2004AFAIL
DetailsSteven Webb
###-#### Larry C/N issued. 2/24/2004 12:16:28 PM
BLD - Request for Extension11/18/200311/18/200311/18/2003PPART
DetailsDave Hannah
###-#### Larry ok to ext 11/18/2003 2:46:31 PM
BLD-Grading Inspection11/17/200311/17/200311/17/2003 PASS
DetailsRita DeYoung
Final grading and drainage approved.
BLD - Request for Extension10/21/200310/22/200310/22/2003APASS
DetailsDave Hannah
work still in progress larry cell ###-#### ok to ext 10/22/2003 8:50:38 AM
BLD-Conference9/8/20039/8/20039/8/2003PPART
DetailsDave Hannah
###-#### larry
Extend Permit 180 days 6/2/20036/2/2003 DONE
Per homeowner, needs about 2 more months to finish this house. Permit extended.
BLD-Conference9/18/20029/20/20029/20/2002PPART
DetailsTony Young
Vern ###-#### call to meet there
conf. on final, procedure 9/20/2002 2:53:44 PM
BLD-Energy code compliance3/4/20023/5/20023/5/2002APASS
DetailsTom Arcoraci
###-####
BLD-Framing/Rough-in3/4/20023/4/20023/4/2002PPART
DetailsTony Young
###-#### VERN
c/n still posted, ok to insulate 3/4/2002 12:52:41 PM
BLD-Framing/Rough-in2/25/20022/25/20022/25/2002PPART
DetailsTony Young
###-####
prior c/n ok,, new c/n posted,, ok to insulate 2/25/2002 2:32:16 PM
BLD-Framing/Rough-in2/20/20022/21/20022/21/2002PFAIL
DetailsTom Arcoraci
###-#### VERN needs to re submit cn posted not per plan 2/21/2002 3:02:48 PM 2/21/2002 3:03:17 PM
BLD-Framing/Rough-in2/20/20022/20/20022/20/2002PCANC
DetailsJim Storey
###-#### VERN ele not insp. 2/20/2002 4:20:20 PM
BLD-Framing/Rough-in2/14/20022/15/20022/15/2002PPART
DetailsJim Storey
###-#### mark exterior ok for cover. 2/15/2002 3:13:00 PM
BLD-Conference1/29/20021/29/20021/29/2002PPART
DetailsTony Young
LARRY ###-####
conf on framing issues/violations, etc.,, also ok to add wall on north side of above garage to gain more head room for storage area 1/29/2002 3:02:13 PM
BLD-Aging Inspection12/18/200112/18/200112/18/2001 PART
DetailsTony Young
wip 12/18/2001 11:14:43 AM
BLD-Foundation10/18/200110/18/200110/18/2001PPART
DetailsTony Young
###-#### VAN REBAR FOR WALLS
basment walls, wip 10/18/2001 1:55:36 PM
BLD-Grading Inspection10/9/200110/9/200110/9/2001 PASS
DetailsRita DeYoung
Geotechnical engineer has approved the footing subgrade.
BLD-Footing10/5/200110/8/200110/8/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/05/2001 at 15:02:13. Contact: . pending eng letter for soils and ok from t. records 10/8/2001 4:13:05 PM