Permit Information
Permit NumberBLD01-02145
StatusFinaled
Name IDAHO POWER
Site Address 204 S 3RD ST
Project NameIDAHO POWER SUB-STA.
Customer Number 
ePlanReviewNo
Description
IDAHO POWER GROVE SUBSTATION ADDITION - TO CONSTRUCT A 175 SQ. FT., ONE STORY BATTERY ROOM ADDITION ON THE NORTH SIDE OF THE EXISTING 410 SQ. FT., ONE STORY ELECTRICAL SUBSTATION CONTROL ROOM; AND INSTALL NEW WOOD SLEEPERS AND METAL ROOF DECKING OVER THE EXISTING CONCRETE TEE ROOF AT THE CONTROL ROOM AREA. THE NEW ADDITION IS CONSTRUCTED OF A CONCRETE FOUNDATION AND SLAB FLOOR, MASONRY EXTERIOR WALLS, TJI ROOF JOISTS WITH OSB SHEATHING AND METAL ROOF DECKING. ALL CONSTRUCTION PER THE APPROVED PLANS. PC#0650-01 JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection6/26/20036/26/20036/26/2003 DONE
DetailsCarl Dependahl
work complete per scope of work...unable to contact contractor 6/26/2003 9:47:34 AM 6/26/2003 9:50:10 AM
BLD-Final2/14/20022/19/20022/20/2002APART
DetailsCarl Dependahl
fn occ- russ -###-####; struct final ok, pending letter from Idaho Power. (Work is at Sub-station) 2/21/2002 8:56:29 AM
FIRE-Final Inspection2/14/20022/15/20022/15/2002APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 02/14/2002 at 16:27:12. Contact: ###-####.
BLD-Final1/30/20021/31/20021/31/2002ANR
DetailsCarl Dependahl
###-#### PLEASE CALL FIRST
Code Occupancy Approval1/31/20021/31/20021/31/2002PPASS
DetailsWm. Michael Meloy
Scheduled by Inspector: WMM On 1/31/2002 12:08:01 PM
FIRE-Final Inspection1/31/20021/31/20021/31/2002AFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 1/31/2002 8:08:47 AM need signs complying with UFC 6404.7 on doors to battery room. 1/31/2002 9:00:14 AM
FIRE-Final Inspection1/30/20021/30/20021/30/2002PNR
DetailsRick Jackson
###-#### rescheduled for 1/31 1/31/2002 8:08:32 AM
BLD-Final1/29/20021/29/20021/29/2002PFAIL
DetailsCarl Dependahl
RUSS ###-####...fail, add landings at door(s) as shown, obtain other finals 1/29/2002 2:32:05 PM
BLD-Aging Inspection1/28/20021/28/20021/28/2002 NR
DetailsCarl Dependahl
Id Power sub-station 1/28/2002 2:05:20 PM
BLD-Aging Inspection11/28/200111/28/200111/28/2001 NR
DetailsCarl Dependahl
wip 11/28/2001 6:08:20 PM
BLD-Framing/Rough-in9/28/20019/28/20019/28/2001PPART
DetailsCarl Dependahl
RUSS ###-####; roof ok 9/28/2001 4:59:52 PM
BLD-Framing/Rough-in9/24/20019/25/20019/25/2001APART
DetailsCarl Dependahl
russ###-#### please call him first ...masonry walls, met arch onsite...need dowel bars to exist bond beam, ok to grout. NO specs called out for f'c or spec insp??? 9/25/2001 11:07:28 AM
BLD-Foundation9/17/20019/18/20019/18/2001PPASS
DetailsCarl Dependahl
RUSS ###-#### bar ok 9/18/2001 6:22:24 PM
BLD-Foundation9/14/20019/17/20019/17/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 09/14/2001 at 11:58:22. Contact: ###-####.
ftg ok, after verbal corrections 9/17/2001 9:31:02 AM