BLD-Final | 1/2/2004 | 1/5/2004 | 1/5/2004 | P | PASS |
Russ Owen
|
|
|
dave- ###-#### --pending fire fn. ok perm oc. 1/5/2004 2:44:58 PM
|
FIRE-Final Inspection | 1/2/2004 | 1/5/2004 | 1/5/2004 | A | PASS |
Rick Jackson
|
|
|
dave- ###-####
|
BLD-Aging Inspection | 11/24/2003 | 11/24/2003 | 11/24/2003 | | NR |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 9/24/2003 | 9/24/2003 | 9/24/2003 | | NR |
Tom Arcoraci
|
|
|
needs fire approval 9/24/2003 3:46:57 PM
|
BLD-Aging Inspection | 7/23/2003 | 7/23/2003 | 7/23/2003 | | CANC |
Tom Arcoraci
|
|
|
waiting for fire app 7/23/2003 9:54:58 AM
|
BLD-Aging Inspection | 4/29/2003 | 4/29/2003 | 4/29/2003 | | PASS |
Tom Arcoraci
|
|
|
waiting for fire approval 4/29/2003 3:17:22 PM
|
BLD-Conference | 4/29/2003 | 4/29/2003 | 4/29/2003 | A | NR |
Troy Cobbley
|
|
|
I spoke with Dave Brice and he stated that Charlie with SimplexGrinnell was working on submitting the drawings. I called Charlie and he said he had not be given the go ahead for design. I told him to follow up and get back to me asap. 4/30/2003 2:44:09 PM
|
FIRE-Conference | 12/31/2002 | 12/31/2002 | 12/31/2002 | A | DONE |
Troy Cobbley
|
|
|
I met with Dave with Brice Construction ###-#### at the job site about getting things wrapped up. No approved drawings were on site for any inspection. He is to get everything together and call in for the inspection. He showed me some fire alarm work that was done in conjunction with this work and there appears to be NO fire alarm permits. The work was done by Charlie at Protex. Dave said he would follow up.
|
BLD-Framing/Rough-in | 3/18/2002 | 3/19/2002 | 3/19/2002 | A | PART |
Tom Arcoraci
|
|
|
###-#### dave call when you get there for access steel studs ok for cover pending elec 3/19/2002 10:38:03 AM
|