BLD-Final | 12/28/2001 | 12/31/2001 | 12/31/2001 | P | PASS |
Jim Storey
|
|
|
Roy, ###-#### final ok. 12/31/2001 1:55:31 PM
|
BLD-Final | 12/28/2001 | 12/31/2001 | 12/31/2001 | P | PASS |
Jim Storey
|
|
|
Roy, ###-#### final ok. 12/31/2001 1:55:31 PM
|
FIRE-Final Inspection | 12/28/2001 | 12/31/2001 | 12/31/2001 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 12/31/2001 1:03:13 PM
|
BLD-Final | 12/28/2001 | 12/28/2001 | 12/28/2001 | P | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 12/28/2001 2:45:49 PM . Needs plans that are legible,a scaled down faxed copy at site is not clear, also needs electrical and fire/life safety inspection. NOTE: this permit is for the canopy fuel island only separate permits are for the carwash and store, Also note this contractor is not the same one as for the other buildings. 12/28/2001 3:35:07 PM 12/28/2001 3:41:48 PM
|
BLD-Footing | 10/31/2001 | 11/1/2001 | 11/1/2001 | A | PASS |
Russ Owen
|
|
|
###-####
|